malec
Dec 6, 2005, 8:37 AM
Please change the status of Almas tower to U/C

You wanted proof? Well here it is! :yes:

Piling Completed; Excavation at the centre core is complete and piles are trimmed; Partial blinding has commenced; Excavation is 70% complete.
The construction of the Almas Tower is anticipated to be complete towards the end of June 2007.
[/list]
http://www.dmcc.ae/images/progress_almas_oct.jpg

November 2005


Piling, ramp access to excavation raft level and excavation at the centre core are 100% complete.
80% of excavation at Pile caps is completed. 70% of Piles cut is completed.
Blinding at Pile caps is in-progress, concreting to raft slab commencing this month.

http://www.dmcc.ae/images/progress_almas_nov.jpg

Patrick
Dec 8, 2005, 12:47 AM
done