[St. John's] 351 Water Street | 12 Floors | U/C
351 Water Street, East Port Properties - Woolworth's Site Office Development
11-12 stories, 46.6 meters (top of mech. penthouse), 6 parking levels, retail and about 160,000 sq ft of class A office space. Developers website: http://threefiftyone.ca/ This project is already under construction. The development will front on Water Street and Harbour Drive. Announced Feb 4th, 2010; this is an office/retail/parking development on the old Woolworth's Dept. Store site. View from Harbour Drive Source: http://threefiftyone.ca/ Building Heights From Harbour Drive, From Water Street Parking Levels 19.1 metres, 15.5 metres Office Levels 24.1 metres, 24.1 metres Total to main roof parapet - 43.2 metres, 39.6 metres Top incl. mech penthouse, Water Street - 43.0 Top incl. mech penthouse, Harbour Drive - 46.6 metres Source: Land Use Assesment Report for 351 Water Street: http://www.stjohns.ca/pdfs/1832-01%2...20May%2028.pdf |
Cool :) Btw, for ease of readability I've changed to prefix to [St. John's] and title to [St. John's] 351 Water Street | 12-floors | Proposed to coincide with the thread naming guidelines in place in SSP:Locals. What do you guys think?
|
Good, thanks. :)
|
Looks good, now we just need some pictures of the progress
|
There are a few construction pictures floating around the St. John's general thread, I'll check for them after. Progress has been going slowly on the site for months now, though I suspect this is due to the complexity of the grade and requirements for the parking garage.
|
Quote:
|
Quote:
|
They had those huge pipes too coming from the ground, I don't know what they were for exactly but there's nothing like them at the Fortis site.
|
Quote:
|
The pics are on Page 171 of the St John's thread. The huge piles they were driving for most of 2010 were for foundation support. That lot is all fill of various ages. I think it took longer than expected to reach solid footing for a building the size of what is going there.
|
Just drove by 351 this afternoon. Very busy today. I saw at least ten people as I drove by.
|
I believe the 300 tonne crane is arriving onsite next week, and the pre cast blocks are going to start arriving in the first week of April. It should start gaining steam quickly now.
|
There's something concrete built up in the centre of the site.
|
Quote:
|
Quote:
The plans suggest that the same elevators will be used for both parking and office floors. |
The site is looking much more organized now. Scrap/junk has been hauled away, the 1st floor garage walls are just about complete on the east and west sides, and much of the ground has been compacted inside. Glad to see that things will soon starting looking "up".
|
Signs are posted downtown, closing Harbour Drive March 26 thru March 28.
Assuming this means the arrival of precast panels..?!? :cool: |
That's just for crane setup. The precast will be arriving over a 6-8 week period.
|
Quote:
|
Quote:
|