I was curious about this, and after some googling, found this
very detailed project schedule from Webcor.
The most recent tasks on the schedule for June/July are:
Quote:
Backfill Bsmt to Street Level Slab and Demo
Mobilize for Drilled Shaft Install
|
And then from July through late October:
Quote:
Install 32 EACH Drilled Shafts (2 per week)
|
So, it's all part of the plan to begin 16 weeks of drilling.
In case that link goes down, the other highlights are:
- Excavation: November 2017 to April 2018
- Crane goes up: April 2018
- Mat pour: June 2018
- Rebar above ground: October 2018
- Level 48 concrete pour: August 2019
- Level 48 curtain wall: October 2019
- Crane dismantled: December 2019
- Certificate of occupancy: June 2020