I was curious about this, and after some googling, found this very detailed project schedule from Webcor.

The most recent tasks on the schedule for June/July are:

Quote:
Backfill Bsmt to Street Level Slab and Demo
Mobilize for Drilled Shaft Install
And then from July through late October:

Quote:
Install 32 EACH Drilled Shafts (2 per week)
So, it's all part of the plan to begin 16 weeks of drilling.




In case that link goes down, the other highlights are:
  • Excavation: November 2017 to April 2018
  • Crane goes up: April 2018
  • Mat pour: June 2018
  • Rebar above ground: October 2018
  • Level 48 concrete pour: August 2019
  • Level 48 curtain wall: October 2019
  • Crane dismantled: December 2019
  • Certificate of occupancy: June 2020