The typical system on this project is a window wall. I'm not sure about the glass that has been installed on the shearwalls though. That might be curtainwall. On a typical construction schedule, the windows are usually scheduled 1 week per floor per installing crew. The crews can work longer hours and weekends to decrease installation durations so long as the window fabricator can keep feeding the windows at the same pace as the installers. With window wall you can start on multiple floors like the other large project with screwed up windows in town (NEMA). On that project, they still haven't caught up and that started several weeks ago. My guess is that the turnover dates on this project are delayed 6 months plus or minus a couple months. Just a guess though...