View Single Post
  #5242  
Old Posted Feb 10, 2018, 4:52 PM
delts145's Avatar
delts145 delts145 is offline
Registered User
 
Join Date: Aug 2006
Location: Downtown Los Angeles
Posts: 19,380
Downtown Adj. - East Central and 9th and 9th projects nearing completion


Isaac Riddle Reports - Full Article @ https://www.buildingsaltlake.com/in-...-completion/3/

Liberty Blvd.

https://i2.wp.com/www.buildingsaltlake.com/

The latest development by Cowboy Partners in Salt Lake City, Liberty BLVD, is well underway and currently pre-leasing. The project replaces a former Wonderbread factory and will have 267 units and 4,000 square feet of commercial space on 400 South. The sprawling project has street frontage on 400 South, 700 East and 500 South and sits just west of the idiosyncratic Gilgal Gardens.


The north side of the Liberty BLVD Apartments as seen looking west on 400 south towards 700 East. Photo by Mike Fife.


A large variety of materials and a mix of their design patterns are being used to sheath the mass transit adj. Liberty Blvd. Pictured, the north facade of the Liberty BLVD Apartments on 400 South just east of 700 East. Photo by Mike Fife.


Haxton Place Apartments


https://images1.apartments.com/

The Haxton Place Apartments is framed out at 900 East and Haxton Place just south of South Temple. The three-story 39-unit project is much smaller project than originally proposed. Initially, the developers, Baron Equities, proposed a five-story 105 unit project which they argued fit well with the much taller towers to the north and south. These older, taller projects were mistakes not to be repeated, according to area residents, particularly those residing in the historic homes on Haxton Place which borders the project to the east. Earlier this year the Historic Landmark Commission approved the scaled-down proposal...


The under-construction Haxton Place Apartments as seen looking north along 900 East from 100 South. Photo by Mike Fife.


Crews constructed a significant retaining wall on the east side of the property and you can see one of the historic homes on Haxton Place to the east beyond the wooden fence. Photo by Mike Fife.


Haxton Place Apartments are on the east side of 900 East, south of South Temple. Photo by Mike Fife.


Mutual Beauty Mixed - Use Development


Rendering of the southeast corner of the Mutual Beauty Project...https://i2.wp.com/www.buildingsaltlake.com/

The 9+9 Mixed-use Development is actively under construction on the corner of Harvey Milk Blvd (900 South) and Lincoln Street in the heart of the Ninth and Ninth Business District. The project replaces a small surface parking lot and a building that had formerly housed a beauty supply business. A Conditional Building and Site Design Review was originally denied for this project, but the Planning Commission’s denial was overturned on appeal.

The three-story project will have retail and structured parking on the ground level below two floors with 28 apartments.



The Mutual Beauty mixed-use development is just east of the existing commercial buildings on the south side of 900 Street. Photo by Mike Fife.



Green fencing encloses the construction site for the Mutual Beauty mixed-use development on Harvey Milk Blvd (900 South) at Lincoln St. Photo by Mike Fife.


Construction of the parking structure is underway on the Mutual Beauty mixed-use development on Harvey Milk Blvd (900 South) and Lincoln Street. Photo by Mike Fife.


1105 East Development


Project rendering of the 1105 East project courtesy Northstar Builders...https://www.buildingsaltlake.com/in-...-completion/3/

Developers, Northstar Builders, have a new project under construction on the east end of the 9th and 9th Business District on the northeast corner of 1100 East and Harvey Milk Blvd (900 South). The project is a two-story commercial building that will house a law office and a design firm and is less than a block to the east of the another Northstar project, the recently completed two-story commercial building on the northwest corner of McClelland Street and 900 South. The building houses Northstar’s offices on the second floor and the Alamexo Cantina and real estate office on the ground floor.


The northeast corner of the 1105 East project. Photo by Mike Fife.


An earlier Northstar Builders project on the northeast corner of Harvey Milk Blvd (900 South) and McClelland Street, a half block west of the 1105 East project. This building serves as Northstar Builders’ HQ and is also home to a real estate company and restaurant. Photo by Mike Fife.

.

Last edited by delts145; Mar 7, 2018 at 3:25 PM.
Reply With Quote