Dec. 19 2017 pictures:



^^^^ Forming the 14th floor. Tie-back installed on gray crane. By my rough calculation they completed 12 condo floors in approx. 16 weeks, or approx. 9.5 days per floor.

A few days ago I noted they were excavating along the east side of the parkade. The hole is not all that big and is now covered with some tarps. So its probably not a big issue (unlike last time they did this).



^^^^ Construction elevator going up on the north side of the hotel. There is a surprisingly large pile of dirt accumulating from the office tower parkade shoring. No digging yet.