^no they are still digging. what is quoted is the "plan" for what will happen

i guess i never posted the second update from webcor. It is over a month old but this is it....

UPDATE

We currently have 2 tower cranes planned 2 double man lifts for the high rise and 1 single car for the mid rise.

Webcor concrete has planned for a Peri self climbing elevator core system for the high rise and 2 sets of flying forms. We are currently planning to hand set the forms for the mid-rise gang forms, etc, but no flyers or self erecting core systems.

The garage is an internally braced soil cement slurry wall system with soldier piles 5’ OC and the High Rise foundation is a soil cement slurry wall system with soldier piles 5’ OC with a few rakers and the balance of the hole supported with a single row of tiebacks. Both of these perimeter wall systems are augured 3’ diameter overlapping holes creating a continuous wall.

We are currently showing a 5 day floor cycle for the construction of the high rise, and a 5 day per floor cycle for the curtain Wall and all interior finishes.

Demolition had has been completed Thursday, September 15, 2005, and the Excavation phase of the project will begin Monday, September 19, 2005.