Quote:
Originally Posted by Skybean View Post
March 2008
Construction continues on schedule. Concrete for the 17th, 18th and 19th floors of the tower portion are being poured. Concrete for the 2nd and 3rd floors of the podium section are being poured. Glass curtainwall for the 10th, 11th and 12th floors is being installed. Elevator installation will continue in the high rise bank and service elevators. Mechanical and electrical trades will continue with their rough ins throughout the tower floors. The adjacent Ritz Carlton development will continue pouring the ground and 2nd floor slabs





source: http://www.rbccentre.ca/