Specifications
Airport Terminal Building size: Approximately 51,000 m²
Parking structure: 4 level parking facility, 1,559 stalls
Airside construction: additional aircraft parking apron
Groundside site services
Project schedule:
2005-06 Roadways/Site works
2005-06 Parkade
2006-09 Airport Terminal Building (Phase I)
Cost:
$572 million range [parking & terminal plus roadways, civil site works and infrastructure] 2003-09