Quote:
Originally Posted by ardecila
$50 million? Morgan only cost $38 million, and it was elevated above a street with no room for construction staging. Plus, that was a very generous budget. I'm sorry, but costs don't rise 30% in 2 years.
|
Guys, published cost figures like these are basically never apples to apples for a laundry list of reasons impacting what is being included in the "all-in" project cost. For example, the Morgan
project cost $38m, but the actual construction contract to the general contractor to build it was $25.3m.
In other CDOT station news, the construction contract for the Clark/Division rehab was just awarded for $41.4m.