At the press conference, a reporter asked about CP's claim the site was winterized and the city basically answered that they expected work to continue through the winter.

Quote:
Originally Posted by LeaderPost
“The city is preparing to take action to require the property owner to backfill the site,” Folk said, explaining that would mean they would need to “fill the hole” left by stalled excavation work.

But there are several steps before that point. It all hinges on the engineering firm working on the project: Isherwood Geostructural Engineers. She said the firm is requiring “specific action” by April 30 and a plan by March 30.

“What this means is by March 30, the property owner has to advice their engineer that it intends to resume construction in April,” said Folk.

She did not comment further on what kind of action would be required.
http://leaderpost.com/news/local-new...capital-pointe

I would love to know what CP has to do specifically to avoid the city backfilling. I'm hoping the city is finally at the end of their rope with this.