Quote:
Originally Posted by RWSMADCONC View Post
The sheeting in the photo from Summersm is to allow excavation to the bottom of the lowest part of the core mat. The core mat has a 10 foot step in it, and will be placed in two pours. The lower portion is at bottom elevation -3.0 ft city datum, the site is at about +10.0 so the excavation needs to be sheeted to keep accessible areas around the deep part of the mat excavation. The bottom of the balance of the mat is at elevation +7.5, top of mat at +14.5, so the cut will be pretty minimal.

The core mat is 7 feet thick, with top of mat at elevation +14.5 except for the low portion of the mat, which is lowered to +4.0 for pits for the high-rise elevators that will service the residential levels above 28.

There are 19-8 foot diameter drilled piers under the core mat, that have bottoms around elevation -42.0 or so. The three that are exposed in Summersm's photo are in the low portion.
Ok, who let the guy in that knows what he is talking about? I'm not sure we can have this!