Quote:
Originally Posted by waterloowarrior View Post
staff report on the Algonquin College Transitway station

it explains some of the phasing and cost info
In that report, the numbers don't add up for me. I looked through costing tables 1 through 4 and they seem to have many repeated steps. I assume that once the Navaho watermain is moved, for example, it doesn't need to be moved again. Also, there seems to be a $98.5M BRT cost that might be the $68.5M cost that is supposed to be included (maybe transcription error). And, ofcourse, the $65.5M would already have the contingency and engineering added so it couldn't just be inserted.

Any way, if I add up the unique items, the cost is 'only' about $134M - not the $185M.

Could some one else take a look and let me know if I'm reading it wrong?