The work at the Riviera Project (a 10 km coastal 4 lanes road) will start this spring.
The first phase will connect the Tomis Yachting Marina to Fincogero Towers.
Also near the Pencil Tower there will be a cableway on the seawall that will link the promenade with the beach.

The next phases consist in new segments of the road and the most important and spectacular a suspended bridge over the sea and a small marina.

The first phase sketch :




The entire project :













Currently they are working on the final phase (in the fincogero project no 1 and will start working at phase one in the spring, leaving the bridge for the end.
The project should be completed in 2015.