Originally Posted by DJ1272 View Post
What is the holdup with progress on 151 Fremont?
You should be addressing that on the 181 Fremont thread however what holdup? They are installing the glazing (windows) and just about every day there's a new row of windows in place on the construction cam . They appear to be working on the 9th row from the top now.

Some days the weather may be too bad (windy, mainly) for operation of the cranes so that could cause one-day delays for both Salesforce and 181 Fremont.