Posted Jul 4, 2012, 5:01 PM
|
Registered User
|
|
Join Date: Oct 2009
Location: St. John's, Newfoundland
Posts: 265
|
|
The precast parking structure and the office building are being performed by two different contractors - the precast contractor is finished and now the office building contractor has begun the steel work. The sixth level of the parking garage appears in fact to be steel construction and I presume would be part of the second contractor's scope. The sixth parking level has actually started along the western edge of the structure (didn't stop for a picture of that... sorry).
A bit more of the vertical steel completed today actually (a couple of levels above the garage) - hope to see it move quickly from here.
|