Quote:
Originally Posted by VivaLFuego View Post
Guys, published cost figures like these are basically never apples to apples for a laundry list of reasons impacting what is being included in the "all-in" project cost. For example, the Morgan project cost $38m, but the actual construction contract to the general contractor to build it was $25.3m.

In other CDOT station news, the construction contract for the Clark/Division rehab was just awarded for $41.4m.
So they can rebuild a subway station for $41.4M in one of the city's most congested areas, but the elevated one with tons of room for staging costs $50M.

I get your point about apples-to-apples, but I'm trying to imagine what kind of extras are included to bring the project up to $50M. Cermak streetscaping? Track renewal? Maybe there's something in the RFP.

Actually, that figure for Clark/Division is phenomenally low if it includes both the new mezzanine and the rehab of the existing one.