The new terminal building will be built in the "midfield" area of the airport property, between the two main existing runways. The $974 million project includes a new terminal, concourse, and parking garage, as well as site preparation, utility and road work, and airfield improvements.
Construction on the terminal began this past July and will be complete in 2008.
Construction on the new airport control tower is complete and will open in 2006. It will be one of the tallest in the world at 340 ft.
KEY INFORMATION
Master Architect: Hellmuth, Obata + Kassabaum, Inc.
Area: 1.2 million square feet
Retail space: 90,000 square feet
Office space: 55,000 square feet
40 passenger gates
96 passenger check-in counters
18 passenger screening checkpoints