Providing BRT services along the two identified routes is estimated to have a capital cost of $480 million, including for construction and maintenance, and servicing and storage facility (improvements), and 25 additional articulated hybrid buses (estimated cost of $900,000 each). Operating costs are estimated to be $80/revenue hour/vehicle. Based on MoveOntario 2020, Provincial and Federal funding for capital for rapid transit along these two corridors could be expected, but the amount to be expected is still to be determined.

The construction costs for BRT are based on an estimate of $6.5 million/km for one-way streets, and $9 million/km for two-way streets.

Providing LRT services along the two identified routes has an estimated capital cost of $1.1 billion, including construction, bridge improvements, Escarpment crossing tunnels and a new garage or storage facility. The cost for Light Rail Vehicles is estimated to be $4 million each. Operating costs are estimated at $175/revenue hour/vehicle. Funding from the MoveOntario 2020 initiative is also expected, at the levels indicated above for BRT.

The construction costs for LRT are based on estimates of $15 million/km for one-way streets and $25 million/km for two-way streets. It should be noted that Hamilton can request additional funding from Metrolinx, or other Provincial or Federal programs as appropriate.