Lobby Ceiling complete



Mural restored



Original medallions were too far gone to save. They were re casted using original plaster & horsehair methods, then hand painted in place. Behind the medallions are hidden HVAC vents for the added A/C and Heat.



Restaurant ceiling is restored. This originally was partially collapsed, and was covered by a drop ceiling from the 50's!



West Mechanical Room nearly completed


Paradise! Graffiti from the decades remains in the basement.


2nd floor office cube. Note the restored ceiling.


West roof tear off complete. Trying to beat the rain!




Mockup of the metal panel and framing system to encase the added seismic supports for the parapet wall




Window restoration in progress. Painstaking process, so many windows


1 of 4 air handlers in the attic. This required cutting a hole in the roof and hoisting at night.


New baggage area