Mitsubishi construction still on schedule, company reports
Memphis Business Journal


Quote:
“The factory designs are complete, the site is prepared and construction is well under way. The last of the 6,000 support pilings will be installed by the end of April and you will then see the building begin to rise,” Badaracco said in a statement... Should construction remain on schedule, the plant will be commissioned this fall. The 350,000-square-foot steel facility will house manufacturing implements and up to 275 employees when it begins churning out 400-ton electrical transformers.
http://www.bizjournals.com/memphis/n...-still-on.html