Quote:
Originally Posted by Marshal View Post
I have no real answer for you, except that, if survey work is being done in a major way (have you seen them in one spot or all over?) it means that the design process is far from complete - the design team would be waiting for the survey dwgs in order to push the conceptual design drawings forward towards construction documents. For large but simple civil work, this need not take more than a few months.

And no, construction never begins with a surveyor and his one trusty shovel.
I forgot to mention in this thread(I did in the closed Port Mann Hwy1 thread), the surveyors were out every day, for several months starting in December last year. Then there was nothing for the summer months. And now they have been back for several days now.