one grant park is utilizing tables which make it easier to do a floor because you can shave a day off of the process by basically pre-assembling the decking in big pieces (which is what tables are)
they are just pulled out from the previously poured floor, placed on the newly poured floor and then sealed, and then ready for the rebar/utilities

also generally a good deck cycle is 3 to 5 days (im not sure about OGP's cycle though)