CONTRACT 2008-32, CENTRAL VALLEY GREENWAY - SECTION 1, PHASE II
Tenders are invited for the complete reconstruction of 405m of asphalt trail under skytrain between Boundary Road and Gilmore Avenue. The work includes construction of retaining wall and paving 400m of 6.5m wide asphalt pathway with a 2.0m wide strip of stamped/colored asphalt. Approximate quantities are 100 cu.m of common excavation, removal of 2,650 sq.m
of existing asphalt, supply of 250 tonnes of base gravels, 220 sq.m of 450mm thick topsoil with irrigation, 2,050 sq.m of 50mm thick asphalt, 880 sq.m of 50mm thick stamped/colored asphalt, 12 sq.m of Allan Block retaining wall and relocation of 11 existing pathway lights.
|