基隆火車站都市更新站區遷移計畫


Project schedule 65 months, start March 2007 and finish in December 2013, total 65 months and cost 270 million NT dollars.

First stage: Building temporary rail line and platform for Yilan line and Keelung Line.




Second Stage: Building permanent underground station and temporary superstructure






Third stage: Yilan and Keelung services move to permanent underground station. Demolish original Keelung Train Station and construct landscape, road, plaza.