Originally Posted by bulgar View Post
Very highly doubt that - there are two critical must-hit dates: substantial completion and CO (certificate of occupancy). The first requires the building be turned over back to the Owner AND requires contractual payment. The latter, requires the building be inspected and deemed safe before tenants move in. This is typically not the case when construction is still in progress.
Interesting.

IS there any actual evidence that the building is behind schedule? Last that was reported on the matter was, in fact, the opposite.