Wow so that means that this project is starting ahead of schedual?
|
Not really. The Port Authority was in charge of building the new "bath tub" and excavation. Silverstein takes charge in January.
Another look at that schedule:
Foundation Construction............................... January - July 2008
Construction Drawings................................... April 1, 2008
Superstructure to Ground Level....................... July 2008 - January 2009
Structural Steel Erection................................ January 2009 - September 2010
Structural Concrete Tower Core & Slab............. March 2009 - November 2010
Core and Shell Work...................................... September 2009 - December 2011
Curtain Wall................................................. November 2009 - March 2011