Update from the Webcor site:
http://www.webcor.com/current.html?proj_id=242
January 2008
Approximately 220,000 cubic yards of soil were removed from the 4-acre site to make way for the 3-level subterranean parking garage. The 1,100 space parking garage is a joint project with the two Hollywood and Vine developers, Gatehouse Capital and Legacy Partners.
The concrete garage structure is nearing completion and the forming of Level 1 began in late December. All four cranes have been erected as well as six concrete placing booms. Some facts of our progress include:
3500 cubic yards of concrete poured in December
34,000 cubic yards poured to date.
11 million lbs of rebar