Garland data center campus growing with $400 million addition



Project Location

Quote:
Developers of a big Garland data center are increasing the size of the project by 50 percent.

California-based Digital Realty a year ago said it would build a $1 billion high-tech campus near Bush Turnpike. Now the firm has purchased more land for a $400 million expansion of the project.

The addition of 16 acres will grow the Digital Realty project to five, 2-story data centers on 64 acres, making it one of the biggest such facilities in North Texas.
Quote:
The 1.4-million square-foot campus will be built in five phases, each with about 280,000 square feet.