  #2541  
Old Posted Mar 25, 2012, 5:43 PM
yankeesfan1000 yankeesfan1000 is offline
Registered User
 
Join Date: Aug 2010
Location: 10014
Posts: 1,617
That last paragraph is why I think this tower lands a tenant before it's capped. Hopefully once a couple of those mega-tenants sign leases in buildings and fewer large blocks of space become available in these new buildings, those mega-tenants will sign leases with increasingly frequency, ensuring that they have space once their lease expires. Thanks for the article.
     
     
  #2542  
Old Posted Mar 25, 2012, 6:07 PM
Dac150's Avatar
Dac150 Dac150 is offline
World Machine
 
Join Date: Sep 2006
Location: NY/CT
Posts: 6,749
And there's ample time for Silverstein to find a tenant to cover the minimal amount - remember also that he has a great advantage over his competitors as that article points out . . . there's physical steel and concrete to already be shown for.
__________________
"I'm going there, but I like it here wherever it is.."
     
     
  #2543  
Old Posted Mar 26, 2012, 7:49 PM
NYguy's Avatar
NYguy NYguy is offline
New Yorker for life
 
Join Date: Jul 2001
Location: Borough of Jersey
Posts: 51,692
Quote:
Originally Posted by Dac150 View Post
And there's ample time for Silverstein to find a tenant to cover the minimal amount - remember also that he has a great advantage over his competitors as that article points out . . . there's physical steel and concrete to already be shown for.
Yes, while other large towers planned have the advantage of being in Midtown, Silverstein's WTC towers are already a real thing, coming out of the ground. Silverstein has until next year to get a tenant (while they are still working on tower 3), and I'd be very surprised if he doesn't land the lease needed to get full funding for construction by then.
__________________
NEW YORK is Back!

“Office buildings are our factories – whether for tech, creative or traditional industries we must continue to grow our modern factories to create new jobs,” said United States Senator Chuck Schumer.
     
     
  #2544  
Old Posted Mar 29, 2012, 2:58 PM
Empire state of mind Empire state of mind is offline
Registered User
 
Join Date: Jan 2012
Location: New York City
Posts: 56
This is NYC he will find a tenant. Tons of company's will want to move back to lower Manhattan once they see one WTC completed. So much happening down there that I've not seen in a while. I think people feel much safer than before.
     
     
  #2545  
Old Posted Mar 30, 2012, 2:20 PM
The Grand Architect's Avatar
The Grand Architect The Grand Architect is offline
Grand is Golden!
 
Join Date: Feb 2011
Location: Chicago, IL
Posts: 303
Quote:
Originally Posted by Empire state of mind View Post
This is NYC he will find a tenant. Tons of company's will want to move back to lower Manhattan once they see one WTC completed. So much happening down there that I've not seen in a while. I think people feel much safer than before.
Yup, this is why I think so too. I mean, come on! This is New York City for crying out loud! The Financial Capitol of the World!

Anyways, I have been making more WTC animations,

http://www.youtube.com/watch?v=qBt4uMzGw70

Some screenshots of my newest 1WTC animation are below:




     
     
  #2546  
Old Posted Mar 31, 2012, 3:16 PM
NYguy's Avatar
NYguy NYguy is offline
New Yorker for life
 
Join Date: Jul 2001
Location: Borough of Jersey
Posts: 51,692
Long way to go. Not as high as 4, but still higher than 2 (barely visible).

ho_hokus

__________________
NEW YORK is Back!

“Office buildings are our factories – whether for tech, creative or traditional industries we must continue to grow our modern factories to create new jobs,” said United States Senator Chuck Schumer.
     
     
  #2547  
Old Posted Mar 31, 2012, 3:31 PM
SoaringSkylines SoaringSkylines is offline
BANNED
 
Join Date: Feb 2012
Location: 900 Biscayne Bay; Miami
Posts: 182
Are they like right now in the process of still building the other WTC complexes (not 4) higher? It seems like 175 Greenwich hasn't rose in almost 2 months.. They may as well just list it as "On Hold" if nothing is going on.
     
     
  #2548  
Old Posted Mar 31, 2012, 7:02 PM
dar124 dar124 is offline
Registered User
 
Join Date: Jan 2011
Location: Cleveland, OH
Posts: 158
Quote:
Originally Posted by SoaringSkylines
They may as well just list it as "On Hold" if nothing is going on.


There's working being done everyday on the other WTC sites.
     
     
  #2549  
Old Posted Apr 1, 2012, 1:48 AM
BStyles BStyles is offline
Registered User
 
Join Date: Jul 2009
Posts: 557
Quote:
Originally Posted by SoaringSkylines View Post
Are they like right now in the process of still building the other WTC complexes (not 4) higher? It seems like 175 Greenwich hasn't rose in almost 2 months.. They may as well just list it as "On Hold" if nothing is going on.
The core just jumped to another level a couple of days ago. What are you talking about?
     
     
  #2550  
Old Posted Apr 1, 2012, 1:56 AM
NYguy's Avatar
NYguy NYguy is offline
New Yorker for life
 
Join Date: Jul 2001
Location: Borough of Jersey
Posts: 51,692
Quote:
Originally Posted by SoaringSkylines View Post
They may as well just list it as "On Hold" if nothing is going on.
I don't know what makes you think nothing is going on. All you have to do is go down to the site. They are working everyday. It's not supposed to get much higher than it is. I've mentioned that steel is not expected to start rising until May.
__________________
NEW YORK is Back!

“Office buildings are our factories – whether for tech, creative or traditional industries we must continue to grow our modern factories to create new jobs,” said United States Senator Chuck Schumer.
     
     
  #2551  
Old Posted Apr 1, 2012, 3:27 AM
SoaringSkylines SoaringSkylines is offline
BANNED
 
Join Date: Feb 2012
Location: 900 Biscayne Bay; Miami
Posts: 182
Quote:
Originally Posted by NYguy View Post
I don't know what makes you think nothing is going on. All you have to do is go down to the site. They are working everyday. It's not supposed to get much higher than it is. I've mentioned that steel is not expected to start rising until May.
Why isn't the steel not going to rise till May? Whatever happened to them having to "cap" it until they found tenants?
     
     
  #2552  
Old Posted Apr 1, 2012, 4:36 AM
Chapelo's Avatar
Chapelo Chapelo is offline
Registered User
 
Join Date: Sep 2011
Location: San Diego
Posts: 324
Quote:
Originally Posted by SoaringSkylines View Post
Why isn't the steel not going to rise till May? Whatever happened to them having to "cap" it until they found tenants?
Steel isn't going to rise until May because the core has to be completed first. They still have a few floors to go. Once the core is completed, you should see perimeter steel erected.

The cap plan is still in place; the plan for now is to construct the first seven floors and underground retail. This is because there is infrastructure below ground level that's shared with Tower 4 and the Transit Hub.
__________________
We spread out and occupy the cracks in the urban streets.
     
     
  #2553  
Old Posted Apr 1, 2012, 1:23 PM
Davidsam52 Davidsam52 is offline
Registered User
 
Join Date: Jul 2011
Location: Ft. Lauderdale, Florida
Posts: 343
Quote:
Originally Posted by Chapelo View Post
Steel isn't going to rise until May because the core has to be completed first. They still have a few floors to go. Once the core is completed, you should see perimeter steel erected.

The cap plan is still in place; the plan for now is to construct the first seven floors and underground retail. This is because there is infrastructure below ground level that's shared with Tower 4 and the Transit Hub.
This is also the reason T2 was built to grade; its underground infrastructure is needed (and shared) for the entire complex.
     
     
  #2554  
Old Posted Apr 1, 2012, 3:26 PM
aquablue aquablue is offline
BANNED
 
Join Date: Nov 2003
Posts: 1,741
Silly question but, how come T3 has such a large concrete core in comparison to 1WTC?
     
     
  #2555  
Old Posted Apr 2, 2012, 3:36 AM
cityenthusiast cityenthusiast is offline
Registered User
 
Join Date: Oct 2009
Location: Atlanta
Posts: 226
Quote:
Originally Posted by aquablue View Post
Silly question but, how come T3 has such a large concrete core in comparison to 1WTC?
Im pretty sure tower 1's core is larger. But i may be wrong
     
     
  #2556  
Old Posted Apr 2, 2012, 3:38 AM
Roadcruiser1's Avatar
Roadcruiser1 Roadcruiser1 is offline
Registered User
 
Join Date: Jun 2010
Location: New York City
Posts: 2,107
Quote:
Originally Posted by aquablue View Post
Silly question but, how come T3 has such a large concrete core in comparison to 1WTC?
It looks like but it might be because the steel hasn't been erected yet.
     
     
  #2557  
Old Posted Apr 3, 2012, 6:44 AM
Otie's Avatar
Otie Otie is offline
Registered User
 
Join Date: Apr 2011
Posts: 700

Last edited by Otie; Apr 3, 2012 at 8:48 PM.
     
     
  #2558  
Old Posted Apr 5, 2012, 6:41 AM
NYguy's Avatar
NYguy NYguy is offline
New Yorker for life
 
Join Date: Jul 2001
Location: Borough of Jersey
Posts: 51,692
__________________
NEW YORK is Back!

“Office buildings are our factories – whether for tech, creative or traditional industries we must continue to grow our modern factories to create new jobs,” said United States Senator Chuck Schumer.
     
     
  #2559  
Old Posted Apr 5, 2012, 8:45 PM
Roadcruiser1's Avatar
Roadcruiser1 Roadcruiser1 is offline
Registered User
 
Join Date: Jun 2010
Location: New York City
Posts: 2,107
This is the only picture I can provide. Take by me from today.

     
     
  #2560  
Old Posted Apr 7, 2012, 7:48 PM
babybackribs2314 babybackribs2314 is offline
Registered User
 
Join Date: Apr 2006
Location: UWS, Manhattan
Posts: 1,728
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
 

Go Back   SkyscraperPage Forum > Discussion Forums > Buildings & Architecture > Completed Project Threads Archive
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 6:27 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.