Charity Hospital Redevelopment:
went to meeting last night.. wasnt too much new to talk about really!
Main Points: Demo work is to start mid december
Actual Lease Agreement has been delivered to LSU and they hope to sign it at a meeting this Friday in Baton Rouge! I think any public announcements or any plans being filed will hinge on this being signed first! Once you have a deal things can move much quicker!
They have moved to phase 2 for Historic Tax Credits.. they expect full construction to take three years from december 2019... however thats everyhing .. many parts of the building expected to open much sooner...
theres a highschool component in it now and they still mention co working space.
they did mention a bit more about properties that are around charity too