Stadium Site
Regina’s skyline has had a significant change in October with the addition of the third and fourth tower cranes at the Regina Revitalization Initiative – Stadium Project construction site. The stadium project is the first PCL commercial project in Regina to have four tower cranes operating at one time.
The four cranes are 61, 66, 73 and 87 metres high and will be used until the fall of 2015.
To date approximately 160,000 cubic metres of soil has been removed from the site with the excavation on the west side at approximately 11 metres below grade.
In total 815 piles have been installed and 7,600 cubic metres of concrete poured. The number of people working on the site has increased to an average of 115 per day. More than 70,000 hours have been put into the on-site construction since June.
“The progress at the site is very impressive. Every time I’ve driven by it is always filled with a lot of activity. It has been fun to see the first phase of the Regina Revitalization Initiative literally grow up out of the ground,” said Mayor Michael Fougere.