"The Finishing Optimization
Project (FOP) is a $186 million
investment in our Hamilton
operations to build a state-ofthe-
art heavy gauge galvanizing
centre, to be known as #6 Line,
convert a current Galvanize line
to Galvalume, as well as see a
new Temper Mill constructed.
...
#4 Galvalume and #6 Galvanize
Project Manager Elizabeth Shaw
says construction “broke
ground” on the foundation of the
tower for the new Galvanizing
line during the week of June 27.
A group of project members
were on site to mark the
occasion at the line located near
the corner of Ottawa Street and
Beach Road. The tower will be in
construction through the fall and
winter of 2011, while the
mechanical and electrical
equipment will be installed
starting in Q1 2012 and the
project is scheduled to be
completed in Q2 2013."