Now that they have added more info to the site plan, I've noticed they have done something I haven't come across before.
The site plan was split into two phases to fast track the project. Phase I is for the hotel demo, excavation and construction of the underground parking levels. Phase II is for the tower, and I don't believe Phase II was approved yet. Normally projects that are fast tracked have two site plans like this filed in the early stages of the project like with Block 185, Block 71 and Third + Shoal. This is the first time I've noticed this being done at this point. But this is good. They can now begin demo and excavation before the tower site plan is approved. I really think this should be getting underway soon because the demo is permitted. It would make no sense to do this unless they were planning to start very soon.
This is from the Phase I approved site plan.