*The following information was last updated on May 27, 2011.
Facade pre-cast panel installation now above floor 13;
windows installation started late May 2011
Concrete floor slabs at floor 15
Elevator and utility work proceeding in the building
Steel topped out March 23, 2011
An exterior hoist is in place on West Broadway
Foundation work concluded in August 2010
Decontamination / cleaning took place from March 2008 to May 2009. Deconstruction ended in November 2009.
Construction manager Hunter-Roberts mobilized construction in January 2010.