Quote:
Originally Posted by Bombardier
They have around 20 floors to go. At 3 days per floor, they should be topped out some time in January if weather cooperates.
|
By my count there are only about 14 floors left as of today. There are 11 floors per frustum (23 total for the top two frustums when you account for the middle transition floor) and with about 8 already poured (based on photos form last Thursday) on the second to last frustum, I the we're closer to the top.
That said, my contact said topping off would be in late February.
So based on these two bits of information are there more floors on the last two frustums than have been used in all the previous ones? Or perhaps the liquid dampers will take a lot more time to frame out and pour...