May hit street level by the end of June, beginning of July?
|
We're gonna start building the ground floor probrely next week, and that one is gonna take a little bit longer to do, due to changes, beams and some part are gonna be up to 18-20 feet high. And then the first floor is gonna be very long to build to, for the same reasons--beams, heigh and a pool.
We're gonna hit typical floor on the forth floor, then it's gonna go kind of fast as 4 days/per floor.
day 1--- build and poor the walls and column.
day 2--- bring the fly-form up.
day 3--- rebar, electrical, plumber.
day 4--- pour the slab