Construction Progress at The BOWERY Condos + Lofts
The BOWERY is now finishing construction of the 10th floor of the building.
Dates: December 7-11 2015
Monday December 7: Right Forming are forming and pouring vertical elements to support the 12th floor structural slab, North section.
Tuesday December 8: Vertical elements North section supporting 12th floor structural slab being stripped and moved to the South section.
Tuesday December 8: Right Forming are flying deck forms for the 12th floor structural slab.
Construction garbage chute now installed.
Tuesday December 8: Deck forms for 12th floor structural slab being placed.
Wednesday December 9: Deck forms for 12th floor structural slab about 98% complete.
Wednesday December 9: Bottom steel, plumbing/mechanical sleeves, electrical core line and in slab water piping install for about 50% of the 12th floor structural slab.
Wednesday December 9: 12th floor slab now level with building next door.
Wednesday December 9: Service entrance switchboard installed in Hydro vault.
Wednesday December 9: Panels for main electrical room installed.
Friday December 11: Right Forming are pouring and finishing 10th floor structural slab.
We will continue to update throughout the construction process. Thank you for your patience with us, and we look forward to hearing/reading your comments and answering any questions you may have.
Sincerely,
Richcraft Group (Construction Team)