HomeDiagramsDatabaseMapsForum About
     

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation


Reply

 
Thread Tools Display Modes
     
     
  #1261  
Old Posted Jul 11, 2014, 1:02 AM
eternallyme eternallyme is offline
Registered User
 
Join Date: Mar 2009
Posts: 5,243
Quote:
Originally Posted by 1overcosc View Post
Hey, it looks like Hurdman station is going to start construction 3 months early (relative to the original project schedule).

Also, 417 traffic apparently shifting over later this month. That surprises me. While there are large sections of the new lanes that are finished, there are some that look like they need more than a few weeks to finish... but who knows.
If there is a mild winter in 2014-15, they might be able to get well ahead of schedule for a 2017 finish if that trend continues...

That would mean they would have to begin the first round of Transitway closures (Hurdman eastward) by the summer of 2015, so they would need to do the route changes for the April 2015 or June 2015 service changes, not the September 2015 changes.
Reply With Quote
     
     
  #1262  
Old Posted Jul 11, 2014, 12:38 PM
1overcosc's Avatar
1overcosc 1overcosc is offline
Registered User
 
Join Date: Jun 2013
Location: Kingston, Ontario
Posts: 11,482
The official schedule calls for opening in late May 2018. Getting ahead of the game to at least the April 2018 service change cycle is likely IMO. The January 2018 change would be tougher, it would require the city to approve earlier starts to Transitway closures most significantly Hurdman-Laurier. Opening much before that is unlikely in my view given the huge number of dependencies this project has, but who knows, the firms that make up RTG have a very strong track record for early openings.
Reply With Quote
     
     
  #1263  
Old Posted Jul 11, 2014, 6:11 PM
Radster Radster is offline
Registered User
 
Join Date: Oct 2007
Location: Chelsea
Posts: 997
Quote:
Originally Posted by 1overcosc View Post
The official schedule calls for opening in late May 2018. Getting ahead of the game to at least the April 2018 service change cycle is likely IMO. The January 2018 change would be tougher, it would require the city to approve earlier starts to Transitway closures most significantly Hurdman-Laurier. Opening much before that is unlikely in my view given the huge number of dependencies this project has, but who knows, the firms that make up RTG have a very strong track record for early openings.
ie. Canada Line in Vancouver
Reply With Quote
     
     
  #1264  
Old Posted Jul 13, 2014, 4:15 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Ottawa
Posts: 12,329
Construction Summary
Week of July 6




Central Segment

Tunnel

West Portal (Jawbreaker)
  • The roadheader continues excavating in drifts in the Lyon Station cavern.
  • Cavern reinforcement is ongoing and includes umbrella and mesh installation, grouting, and shotcreting.

Central Shaft (Chewrocka)
  • Mining of the Parliament Station cavern transition advances.
  • Pouring of sections of mud slab is ongoing.
  • Tunnel reinforcement continues, including umbrella and mesh installation, and shotcreting.

The application of shotcrete for tunnel reinforcement is ongoing


East Portal (Crocodile Rouge)
  • Installation of tunnel support, including rockbolts and spiles[i], continues as mining advances north under Laurier Street.

For weekly updates on tunnel excavation progress please visit the Roadheader page.

East Segment

Maintenance and Storage Facility (MSF)

Construction activities advance at the MSF as long-term closure of Belfast Road south of Tremblay Road to Trainyards Drive north of Tremblay Road to Coventry Road is ongoing.
  • Site utilities, storm sewer work and backfilling continues.
  • Excavation progresses on the MSF building foundation.
  • Works for the MSF connector continue, including bridge parapet removal, stripping of topsoil, and utilities locates with the VIA right of way.
  • Ongoing MSF connector activities include shoring, piling, lagging, and the installation of monitoring equipment.
  • Utility work south of Tremblay Road is expected to begin.

Civic Works

Highway 417 Roadwork, Widening and Structure Rehabilitation

Roadworks
  • Utilities and sewer work is ongoing along the north and south sides of the highway.
  • From St. Laurent Boulevard to Vanier Parkway panel work progresses for the sound wall along the north and south sides of the highway.
  • Roadway construction continues with excavation, milling[ii], paving, grading and pouring of concrete barrier walls along the north and south sides of Highway 417 from St. Laurent Boulevard to Nicholas Street.

Signage
  • The three message signs have been installed; final construction and electrical works to power the signs continue.

Structures
  • Widening, reconstruction and rehabilitation of various bridge structures along the highway continues to progress.

Hurdman Bridge
  • Paving of the EBL continues.
  • Construction of the approach and sleeper slabs is underway.

Paving at Hurdman Bridge


St. Laurent Overpass
  • Widening and rehabilitation of the structure is ongoing on the south side, with forming[iii] and pouring, rebar installation and stripping.
  • Reconstruction progresses on the north and south off-ramps and includes paving.
  • Installation of the noise wall continues at the northwest on-ramp.

Waterproofing continues at St. Laurent


Vanier Parkway Overpass– work advances in preparation of the rapid bridge replacement scheduled for late September.
  • Work continues in the staging area and includes the installation of reinforcing steel in the deck.
  • The construction of new plinths is underway on the existing structure.

Work continues in the Vanier Overpass staging area


Belfast Road Underpass– Demolition of the existing structure advances as long-term closure of Belfast Road, north of Tremblay Road to Coventry Road continues.
  • Concrete placement of the north-east and south-east parapet walls is underway.
  • Construction of the new plinths is ongoing.
  • Installation of the north span underdecking is underway.

Lees Avenue Underpass
  • Work on the new deck progresses, including concrete placement of the sidewalks and parapet walls and stripping of the deck formwork.
  • Granular and sewer work is ongoing on Robinson Road.

Coventry Pedestrian Footbridge
  • At the north ramp, construction of the footing extension is ongoing.
  • At the south ramp, construction of the vault abutment walls, stair walls and small abutment footing are all underway.
  • Installation of the precast concrete deck panels is in progress.

Coventry Pedestrian bridge


Stay on-track with us and follow our progress by visiting the sections related to each area of construction at the top of this webpage.

[i] Spiles refer to the protective pipe canopies installed to support the tunnel structure.
[ii] Milling refers to the process of removing asphalt pavement with a milling machine.
[iii] Formwork refers to a mold in which concrete is poured.
Reply With Quote
     
     
  #1265  
Old Posted Jul 16, 2014, 5:37 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Ottawa
Posts: 12,329
Construction Summary
Week of July 13


Mining advances under Laurier Avenue from the East Portal


Central Segment

Tunnel

West Portal (Jawbreaker)
  • Excavation of the central pillar in Lyon Station cavern progresses.
  • Cavern reinforcement is ongoing and includes umbrella and mesh installation as well as shotcreting.

Mining central pillar in Lyon Station cavern


Central Shaft (Chewrocka)
  • The roadheader continues mining Parliament Station cavern in drifts.
  • Cavern reinforcement continues and includes umbrella and mesh installation as well as shotcreting.

East Portal (Crocodile Rouge)
  • Installation of tunnel support, including rockbolts and spiles[i], is ongoing as mining continues north under Laurier Avenue.

For weekly updates on tunnel excavation progress please visit the Roadheader page.

East Segment

Maintenance and Storage Facility (MSF)

Construction activities advance at the MSF as long-term closure of Belfast Road south of Tremblay Road to Trainyards Drive and north of Tremblay Road to Coventry Road is ongoing.


MSF site foundation work continues / Les travaux d’excavation continuent à l’IRE
  • Site utilities, storm sewer work and backfilling continues.
  • Excavation progresses on the MSF building foundation.
  • Works for the MSF connector continue, including stripping of topsoil and utilities locates within the VIA right of way.
  • Ongoing MSF connector activities include shoring, piling, lagging, and the installation of monitoring equipment.
  • Utility work south of Tremblay Road continues.

Access track work at the MSF


Civic Works

Highway 417 Roadwork, Widening and Structure Rehabilitation

Roadworks
  • Utilities and sewer work is ongoing along the north and south sides of the highway.
  • From St. Laurent Boulevard to Vanier Parkway panel work progresses for the sound wall along the north and south sides of the highway.
  • Roadway construction continues with excavation, milling[ii], placing and compacting granulars, grading and pouring of concrete barrier walls along the north and south sides of Highway 417 from St. Laurent Boulevard to Nicholas Street.

Roadway construction on north side of Highway 417


Signage
  • The three message signs have been installed; final construction and electrical works to power the signs continue.

Structures
  • Widening, reconstruction and rehabilitation of various bridge structures along the highway continue to progress.

Hurdman Bridge
  • Widening and rehabilitation of the structure continues, with stripping the deck of the eastbound lanes, and stripping the access of the westbound lanes.

Hurdman Bridge rehabilitation progresses on the north side


St. Laurent Overpass
  • Widening and rehabilitation of the structure is ongoing on the north side, with forming[iii] and pouring of the abutments, installation of roadway protection, removal of the approach slab, and chipping out the deck and ballast walls.
  • Installation of the noise wall continues at the northwest on-ramp.

Vanier Parkway Overpass– work advances in preparation of the rapid bridge replacement scheduled for late September.
  • Work continues in the staging area and includes the installation of reinforcing steel on the deck.
  • Preparations for pouring the new bridge deck is underway.

Rebar installation occurs on the neck deck of Vanier Overpass in staging area


Belfast Road Underpass– Demolition of the existing structure advances as long-term closure of Belfast Road, north of Tremblay Road to Coventry Road continues.
  • Formwork and pouring continues at the south abutment.
  • Demolition progresses and includes removal of girders.

Parapet wall at Belfast Road underpass


Lees Avenue Underpass
  • Work on the new deck progresses, and includes forming, stripping and pouring parapet walls, hedge pilling, and removing the overhanging bracket platform on the west side.
  • Granular and sewer work progresses on Robinson Road.

Deck waterproofing advances at Lees Avenue underpass


Coventry Pedestrian Footbridge
  • Construction progresses, and includes the installation of reinforcing cages for the bridge’s columns.
  • At the south ramp, the installation of granular material inside the south vault was completed.

Coventry footbridge south abutment work progresses


Stay on-track with us and follow our progress by visiting the sections related to each area of construction at the top of this webpage.

[i] Spiles refer to the protective pipe canopies installed to support the tunnel structure.
[ii] Milling refers to the process of removing asphalt pavement with a milling machine.
[iii] Formwork refers to a mold in which concrete is poured.

http://www.confederationline.ca/en/c...on-summary-38/
Reply With Quote
     
     
  #1266  
Old Posted Jul 16, 2014, 6:44 PM
MountainView MountainView is offline
Registered User
 
Join Date: Feb 2011
Posts: 1,837
Quote:
Originally Posted by rocketphish View Post
Signage
  • The three message signs have been installed; final construction and electrical works to power the signs continue.
THIS

Every week since the signs went up it's been in final construction of electrical work. Anyone know when they will actually be working so I can be reminded to buckle up for safety?
Reply With Quote
     
     
  #1267  
Old Posted Jul 16, 2014, 7:21 PM
hwy418 hwy418 is offline
Registered User
 
Join Date: Jun 2013
Posts: 342
Quote:
Originally Posted by MountainView View Post
THIS

Every week since the signs went up it's been in final construction of electrical work. Anyone know when they will actually be working so I can be reminded to buckle up for safety?
Apparently there was an issue with getting the "proper" power to some of the signs. Given they were installed late last fall, construction could not resume until this spring.
Reply With Quote
     
     
  #1268  
Old Posted Jul 16, 2014, 7:47 PM
harls's Avatar
harls harls is offline
Mooderator
 
Join Date: Jan 2002
Location: Aylmer, Québec
Posts: 19,699
Quote:
Originally Posted by hwy418 View Post
Apparently there was an issue with getting the "proper" power to some of the signs. Given they were installed late last fall, construction could not resume until this spring.

On Monday night, I noticed a single blue square lit up on the Parkdale sign.
Reply With Quote
     
     
  #1269  
Old Posted Jul 16, 2014, 8:22 PM
MountainView MountainView is offline
Registered User
 
Join Date: Feb 2011
Posts: 1,837
Quote:
Originally Posted by harls View Post
On Monday night, I noticed a single blue square lit up on the Parkdale sign.
I guess that means we'll get one of the newer coloured ones. Thanks for the info guys.
Reply With Quote
     
     
  #1270  
Old Posted Jul 16, 2014, 8:27 PM
hwy418 hwy418 is offline
Registered User
 
Join Date: Jun 2013
Posts: 342
Quote:
Originally Posted by MountainView View Post
I guess that means we'll get one of the newer coloured ones. Thanks for the info guys.
Yep - all Ottawa signs will be full-colour matrix type.
Reply With Quote
     
     
  #1271  
Old Posted Jul 16, 2014, 9:13 PM
ryan1 ryan1 is offline
Registered User
 
Join Date: Jun 2014
Posts: 30
Quote:
Originally Posted by harls View Post
On Monday night, I noticed a single blue square lit up on the Parkdale sign.

+1...saw that driving underneath on Tuesday night (last night). Maybe it already has a stuck "pixel".
Reply With Quote
     
     
  #1272  
Old Posted Jul 16, 2014, 11:10 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 24,011
Apparently RTG accidently punched through the SunLife Building's garage according to Claudia Cauttilo/CTV Ottawa twitter.

Quote:
Claudia Cautillo @ClaudiaCTV

City confirms to @ctvottawa 2 rock bolts went through Sun Life building on O'Connor at Queen during LRT work. #ottnews

City says rock bolts penetrated parking garage of Sun Life building. No injuries, no damage to building integrity, or to garage contents.

Cost of damage/repairs to be picked up by Rideau Transit Group (company doing LRT work).
https://twitter.com/ctvottawa?origin...06305992495106

Last edited by J.OT13; Jul 16, 2014 at 11:37 PM.
Reply With Quote
     
     
  #1273  
Old Posted Jul 17, 2014, 12:02 AM
eternallyme eternallyme is offline
Registered User
 
Join Date: Mar 2009
Posts: 5,243
Looking at the current schedules, the target should be now June 2015 (the service change period then) for closing the East Transitway. They would need the next bus order (whether it be 40 new double decker buses, 58 new articulated buses or 78 new 40-foot buses) in by August 2015 to avoid bus shortages.

I'm not sure what the plan is then, but each has their pros and cons:

Double deckers
PROS: Fewest new buses required; least likely to create downtown capacity issues due to taking up least space; only existing model still created so doesn't add a new model to the fleet; performs well overall in heavy snow
CONS: Not much use after the LRT opens; the 2013 accident report has not been released yet

Artics
PROS: Some use in local routes; long record of use in Ottawa; would be useful through 2027 even after earlier artics are retired
CONS: Useless in heavy snow; creates significant downtown crowding; adds a new model (presumably either Nova LFS Artic or New Flyer Xcelsior Artic)

40-footers
PROS: Most useful on local routes (important after 2018); most new buses added so able to increase frequency in longer term; generally performs well in heavy snow
CONS: Adds a new model (most likely either Nova LFS or New Flyer Xcelsior); creates significant downtown crowding; requires greatest short-term purchase
Reply With Quote
     
     
  #1274  
Old Posted Jul 17, 2014, 12:50 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Ottawa
Posts: 12,329
Quote:
Originally Posted by ryan1 View Post

Quote:
Originally Posted by harls View Post
On Monday night, I noticed a single blue square lit up on the Parkdale sign.
+1...saw that driving underneath on Tuesday night (last night). Maybe it already has a stuck "pixel".
I saw the same blue pixel yesterday morning and again this morning, in the lower left quadrant of the sign. So I guess it's got power.
Reply With Quote
     
     
  #1275  
Old Posted Jul 17, 2014, 1:58 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Ottawa
Posts: 12,329
Ottawa LRT excavation pierces parking garage wall downtown

Ottawa Citizen
Published on: July 16, 2014, Last Updated: July 16, 2014 9:06 PM EDT


Tunnelling for Ottawa’s light-rail transit project hit a bump Wednesday night in the form of a parking garage wall.

Two rock bolts being used during the excavation process penetrated the parking garage wall of the Sun Life building on the corner of Queen and O’Connor streets downtown, a few blocks from Parliament Hill.

Details of how much of a hole were made by the long bolts, which are typically used to stabilize things such as walls, were not immediately provided by Rideau Transit Group, which is in charge of the city’s biggest infrastructure project.

“There are no risks to the integrity of building’s foundation and there was no other property damage,” said Gary Craig, acting director, rail implementation office, in a statement to the Citizen.

“RTG staff are working on a revised methodology to install the rock bolts to ensure there is no re-occurrence.”

He said city staff were working with the property’s owners — Bentall Kennedy — to ensure all necessary repairs get done. Those repairs will be paid for by RTG, Craig said.

A security guard at the building and a staff member at the YMCA located in its basement both said they didn’t feel anything unusual.

http://ottawacitizen.com/news/local-...-wall-downtown
Reply With Quote
     
     
  #1276  
Old Posted Jul 17, 2014, 2:01 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Ottawa
Posts: 12,329
The gantry crane located above the Confederation Line's central shaft:


Wednesday, July 16, 2014. Mike Carroccetto / Ottawa Citizen
Reply With Quote
     
     
  #1277  
Old Posted Jul 26, 2014, 2:46 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Ottawa
Posts: 12,329
Construction Summary
Week of July 20




Central Segment

Tunnel

West Portal (Jawbreaker)
  • Mining of the central pillar was completed.
  • Excavation of the bench and in drifts continue in Lyon Station cavern.
  • Cavern reinforcement is ongoing and includes umbrella and mesh installation as well as shotcreting.

Central Shaft (Chewrocka)
  • The roadheader continues mining Parliament Station cavern in drifts.
  • Cavern reinforcement continues, including umbrella, rockbolt and mesh installation as well as shotcreting.

East Portal (Crocodile Rouge)
  • Installation of tunnel support, including rockbolts and spiles[i], is ongoing as mining progresses north past Laurier Avenue.

Mining advances under Laurier Avenue from the East Portal


East Segment

Maintenance and Storage Facility (MSF)

Construction activities progress at the MSF as long-term closure of Belfast Road south of Tremblay Road to Trainyards Drive and north of Tremblay Road to Coventry Road is ongoing.

MSF site foundation work is ongoing

  • Site utilities, storm sewer work and backfilling is ongoing.
  • Excavation advances on the MSF building foundation and footing.
  • Works for the MSF connector continue, including shoring, piling, and lagging.
  • Installation of monitoring equipment for the MSF connector was completed.
  • Utility work south of Tremblay Road continues.

Piling underway at the MSF access track


Civic Works

Highway 417 Roadwork, Widening and Structure Rehabilitation

During the weekend of July 11, traffic on the eastbound lanes of Highway 417 shifted to the outside lanes to allow for stage 2 of highway works, in which the median lane will undergo rehabilitation, to begin. Work required included paving, obliterating and repainting lines, and shifting the quick moveable barriers (QMB) into the new configuration. The switch to stage 2 for Highway 417 eastbound lanes is ongoing. The westbound lanes switch is scheduled to commence in the beginning of August.

Roadworks
  • Utilities and sewer work is progressing along the north and south sides of the highway.
  • Panel work progresses for the sound wall along the north and south sides of the highway from St. Laurent Boulevard to Vanier Parkway.
  • Roadway construction continues with excavation, milling[ii], placing and compacting granulars, grading and pouring of concrete barrier walls along the north and south sides of Highway 417 from St. Laurent Boulevard to Nicholas Street.

Eastbound lanes between Belfast Road and St. Laurent Boulevard seen after shift to stage 2


Signage
  • The three message signs have been installed; final construction and electrical works to power the signs continue.

Structures
  • Widening, reconstruction and rehabilitation of various bridge structures along the highway continue to progress toward stage 2 of works.

Hurdman Bridge
  • Widening and rehabilitation of the structure continues, with installation of plates on the north side, and causeway construction on the south side.

Pouring underway on the north side of Hurdman Bridge


St. Laurent Overpass
  • Widening and rehabilitation of the structure is ongoing on the north side, with forming[iii] and pouring of the abutments.
  • Installation of the roadway protection installation, sawcutting the ballast wall, and chipping out the deck and ballast walls continue.
  • On the south side, work includes excavation of the deck ends, removal of the ballast wall, and chipping out the deck end and expansion joint.
  • Installation of the noise wall continues at the northwest on-ramp.

Vanier Parkway Overpass– work advances in preparation of the rapid bridge replacement scheduled for September.
  • Work continues in the staging area and includes the placement of supports and excavation to install lagging.
  • Preparations for pouring the new bridge deck are underway.

Belfast Road Underpass– Demolition of the existing structure advances as long-term closure of Belfast Road, north of Tremblay Road to Coventry Road continues.
  • Formwork continues at the north retaining wall.
  • Demolition progresses and includes removal of girders.

Lees Avenue Underpass – construction of the new bridge continues in preparation for the rapid replacement scheduled for September.
  • Work on the new deck progresses; sidewalks on the new deck have been poured.
  • Forming, stripping and pouring parapet walls, partial depth removals of the wingwalls and abutments, and construction of the abutment protection system are ongoing.
  • Granular and sewer work progresses on Robinson Road.

Construction progresses on the new superstructure at Lees staging area


Coventry Pedestrian Footbridge
  • Construction progresses, and includes the installation of reinforcing cages for the bridge’s columns, precast installation, and formwork and pouring of sections of the south abutment.
  • Formwork on footbridge superstructure progresses.

Installation of reinforcing steel cages for columns at Coventry Footbridge


Stay on-track with us and follow our progress by visiting the sections related to each area of construction at the top of this webpage.

[i] Spiles refer to the protective pipe canopies installed to support the tunnel structure.
[ii] Milling refers to the process of removing asphalt pavement with a milling machine.
[iii] Formwork refers to a mold in which concrete is poured.

http://www.confederationline.ca/en/#target6478
Reply With Quote
     
     
  #1278  
Old Posted Jul 29, 2014, 5:18 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Ottawa
Posts: 12,329
Ottawa won't hit the transit re-set button again

Peter Raaymakers
Published on: July 29, 2014, Last Updated: July 29, 2014 1:08 PM EDT


It looks like this October’s municipal election will have at least one thing in common with the last two: A focus on public transit plans among Ottawa’s mayoral candidates.

On Sunday, candidate Darren Wood was profiled by the Ottawa Citizen. His major concern was Ottawa’s financial situation, which Wood believes is so dire that the city must “scrap” the light-rail transit plan that city staff, councillors, and citizens have spent the last eight years refining and constructing. Although Wood’s platform appears to be changing as people engage him through social media or in person, he’s been exceptionally firm on his reluctance to use debt for the sake of infrastructure development like the city’s LRT project.

Wood is actually the second mayoral candidate to take issue with the current plan due to its cost. Mike Maguire, who also ran for mayor in the 2010 election, called the current Confederation Line “erroneously expensive” in an interview with the Citizen. Although he doesn’t mention cancelling the current project (which will run from Tunney’s Pasture to Blair and includes the tunnel that’s currently being bored under downtown), he has pledged to cancel the second phase of the plan in favour of commuter rail using existing rights-of-way — something he also proposed four years ago as an alternative to the current plan. (Maguire also wants OC Transpo “opened up for competition,” which is the same transit privatization plan he set out in 2010.)

Both of these men would be wise to learn from the most obvious lesson of the 2010 mayoral election: The citizens of Ottawa aren’t interested in hitting the re-set button on transit again.

In 2010, Ottawa voters had their choice of 20 mayoral candidates — many of whom, including Maguire, offered their own transit alternatives. Clive Doucet wanted to move back to surface-level LRT, as opposed to a tunnel. Andrew Haydon’s last-minute campaign sought a tunnel for buses instead of trains. Jane Scharf wanted Ottawa to build an electric gondola system. Joseph Furtenbacher proposed light rail along the 417/174 corridor. Transit was the main issue of the election, and there was no shortage of alternative plans for Ottawa voters to choose from.

Yet in the end, voters were strongly supportive of the current plan. Eventual winner Jim Watson secured more than 48 per cent of the vote based on his support of the current plan and his insistence that it not go over budget. Failed incumbent Larry O’Brien also supported the plan we have today, and he brought in another 24 per cent of the popular vote. All told, nearly three-quarters of voters selected candidates who supported the current plan. Although other factors came into play, as well, the result was a resounding pledge of support for the city to move forward on the current plan, with the caveat that costs be controlled and debt-financing be responsible and manageable.

Looking back to the 2006 election, it’s easy to see why the people of Ottawa were not interested in starting all over on transit plans. Larry O’Brien campaigned on re-assessing the plan that Bob Chiarelli had put together to electrify the O-Train and extend the tracks, at street level, north into downtown and south to the airport and through Barrhaven. When O’Brien won, the plan was cancelled amidst much controversy — notably about rising costs, which direction it should go, whether the federal government was fully committed to its funding pledge, and whether Ottawa would be better served with a downtown tunnel.

Cancelling that plan cost the city a reported $36.7 million settlement. It had been signed to a fixed-cost $880-million contract for 29 kilometres of rail lines, as opposed to $2.1 billion for the 12.5-kilometre Confederation Line. Development plans based on the O-Train extension, notably in Barrhaven and Riverside South, were orphaned by its cancellation. And in the end, it set light-rail in the city back by nearly a decade.

But even though the Confederation Line will be long overdue when it is finally fully operational in 2018, we can be thankful that it’s a good plan. It’s expensive, but you get what you pay for, and the investment in a downtown tunnel is worth it — the cancelled O-Train extension might have delayed the need for a tunnel, but eventually one would have been necessary. Although the city is bringing on significant debt to finance it, this is the kind of project worth accumulating debt for. It will modernize Ottawa’s transit infrastructure, and the benefits of the line will be enjoyed by generations. And the $2.1-billion contract is fixed-cost, so any construction-related overruns shouldn’t affect the bottom line for taxpayers in Ottawa.

We’re so far into the Confederation Line that cancelling it would be ridiculously costly. Even making changes to the contract that’s been signed would be expensive. If a motion to cancel the plan were brought forward, it wouldn’t be supported by a council that will probably be populated by a good number of the current councillors who voted unanimously in favour of the Confederation Line.

Voters in Ottawa proved in 2010 they have no interest in once again “hitting the re-set button,” to borrow a phrase from former mayor Larry O’Brien’s 2006 campaign. It seems strange to me that two people who’ve put forward their names to run for mayor have failed to recognize this — especially Maguire, who was told in no uncertain terms during the last election that his plan doesn’t resound with voters. Transit is a pretty big deal in Ottawa.

What’s been interesting to watch has been the evolution of Jim Watson as he’s recognized just how supportive Ottawa residents are regarding major investments in transit. As a Member of Provincial Parliament, Watson was very sceptical about the affordability of the current plan. In the lead-up to his mayoral campaign, he became supportive — as long as the plan’s costs were controlled. As mayor, he doubled down: He’s become the strongest supporter of the Confederation Line and championed its unanimously-supported $2.5-billion extension.

Watson realized some time ago that Ottawa voters are supportive of public transit investments, and that knowledge helped him win the last election. Unless one of the other candidates makes that realization soon, it’s likely the people of Ottawa will give him another one.

Peter Raaymakers is a lifelong Ottawa resident and the executive director of TransitOttawa.ca.

http://ottawacitizen.com/news/local-...t-button-again
Reply With Quote
     
     
  #1279  
Old Posted Jul 29, 2014, 6:05 PM
1overcosc's Avatar
1overcosc 1overcosc is offline
Registered User
 
Join Date: Jun 2013
Location: Kingston, Ontario
Posts: 11,482
What's with this insistence among those fringe candidates that the city has some sort of fiscal crisis? The City of Ottawa's credit rating is literally perfect--AAA.
Reply With Quote
     
     
  #1280  
Old Posted Jul 29, 2014, 11:45 PM
SF Thomas SF Thomas is offline
Registered User
 
Join Date: Aug 2013
Posts: 124
Quote:
Originally Posted by 1overcosc View Post
What's with this insistence among those fringe candidates that the city has some sort of fiscal crisis? The City of Ottawa's credit rating is literally perfect--AAA.
Don't know much about Wood, but Maguire is fairly conservative, namely doesn't like any tax increases or taking on extra debt to fund projects. He has advocated some things I find pretty unrealistic like privatizing individual bus routes in an attempt to bring private sector competition into the bus system.

To be somewhat fair Ottawa is funding a fair bit of the LRT project by borrowing. I don't think there is a really good and cheap transit alternative though, it is also harder to justify trying to change modes since the present LRT plan is so far underway. Once phase 1 is complete it is also a lot easier to build off the existing LRT system.

-----------------------

I don't think what Maguire is advocating, stick with the existing bus system with a few changes and add in some commuter rail on its own is a very viable idea. At minimum the LRT downtown was needed simply because there wasn't enough room to fit the number of buses needed for service during peak periods, even building a bus tunnel like Andy Haydon wanted probably would not have solved the capacity problem. While ending the system at Tunney's for the moment is okay, having an LRT line running only halfway through the core city (the area within the greenbelt) long term would be pretty awkward.

Commuter rail on its own might not be a bad idea, but the existing rail lines in Ottawa aren't very well placed for it. Barrhaven to the Via station is probably the most viable route. The line to Kanata though loops too far south to work well and there is no line to Orleans (and the existing branch we could build off of is again too far south to work well).
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 11:27 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.