Why was AFD there? I would have thought they were assisting in dust control but I don't see any water or wet spots and you wouldn't need two trucks for that.
This is just speculation on my part, but they may be doing training exercises. Seems like busting a hole in the roof of an actual CVS would be much more realistic than any simulation. And why not, it's getting torn down anyhow.
Training makes sense. It's not unusual for fire departments to do that at sites that are about to be demolished. Same thing happened at the old Marble Falls HEB, according to family members who live in the area.
Training makes sense. It's not unusual for fire departments to do that at sites that are about to be demolished. Same thing happened at the old Marble Falls HEB, according to family members who live in the area.
Its more fun when they torch it. I have participated in a few of those, mostly condemned residential though.
Bump... No change for almost three months, site still completely dirt. Haven't seen equipment on since since April. Anyone know anything about the delay?
__________________ It can be done, if we have the will.
Bump... No change for almost three months, site still completely dirt. Haven't seen equipment on since since April. Anyone know anything about the delay?
They have still been working through the permitting process. Just last week they had a site plan change approved for "add temporary construction driveways for site excavation & tower construction." Earlier in the year they had another site plan change approved related to utilities.
Bump... No change for almost three months, site still completely dirt. Haven't seen equipment on since since April. Anyone know anything about the delay?
Even worse, they hauled the port-a-potty away months ago.
Even worse, they hauled the port-a-potty away months ago.
What?! Wait...that is bad news....only one port-a-potty for a large construction site in a town that is known for its Tex-Mex breakfast, lunch and dinners??? Oh the humanity...
Last edited by the Genral; May 3, 2019 at 2:14 AM.
They have still been working through the permitting process. Just last week they had a site plan change approved for "add temporary construction driveways for site excavation & tower construction." Earlier in the year they had another site plan change approved related to utilities.
Good to know. Glad this project is still chugging along.
__________________ It can be done, if we have the will.