[St. John's] 351 Water Street | 12 Floors | U/C

351 Water Street, East Port Properties - Woolworth's Site Office Development
11-12 stories, 46.6 meters (top of mech. penthouse), 6 parking levels, retail and about 160,000 sq ft of class A office space.

Developers website: http://threefiftyone.ca/

This project is already under construction.

The development will front on Water Street and Harbour Drive.

Announced Feb 4th, 2010; this is an office/retail/parking development on the old Woolworth's Dept. Store site.



View from Harbour Drive
Source: http://threefiftyone.ca/


Building Heights
From Harbour Drive, From Water Street
Parking Levels 19.1 metres, 15.5 metres
Office Levels 24.1 metres, 24.1 metres
Total to main roof parapet - 43.2 metres, 39.6 metres
Top incl. mech penthouse, Water Street - 43.0
Top incl. mech penthouse, Harbour Drive - 46.6 metres

Source: Land Use Assesment Report for 351 Water Street:
http://www.stjohns.ca/pdfs/1832-01%2...20May%2028.pdf

Last edited by Architype; Sep 26, 2012 at 10:40 PM.
Reply With Quote
     
     
  #2  
Old Posted Mar 13, 2012, 5:33 AM
Mike K.'s Avatar
Mike K. Mike K. is offline
Registered User
 
Join Date: Feb 2003
Posts: 9,141
Cool Btw, for ease of readability I've changed to prefix to [St. John's] and title to [St. John's] 351 Water Street | 12-floors | Proposed to coincide with the thread naming guidelines in place in SSP:Locals. What do you guys think?
__________________
>>>VibrantVictoria.ca
Reply With Quote
     
     
  #3  
Old Posted Mar 13, 2012, 5:36 AM
Architype's Avatar
Architype Architype is offline
♒︎ Empirically Canadian
 
Join Date: Mar 2004
Location: 🍁 Canada
Posts: 11,902
Good, thanks.
Reply With Quote
     
     
  #4  
Old Posted Mar 13, 2012, 1:37 PM
jeddy1989's Avatar
jeddy1989 jeddy1989 is offline
Registered User
 
Join Date: Dec 2009
Location: St. John's, NL
Posts: 2,711
Looks good, now we just need some pictures of the progress
Reply With Quote
     
     
  #5  
Old Posted Mar 13, 2012, 2:09 PM
Marty_Mcfly's Avatar
Marty_Mcfly Marty_Mcfly is offline
Registered User
 
Join Date: Feb 2009
Location: St. John's, NL
Posts: 7,165
There are a few construction pictures floating around the St. John's general thread, I'll check for them after. Progress has been going slowly on the site for months now, though I suspect this is due to the complexity of the grade and requirements for the parking garage.
Reply With Quote
     
     
  #6  
Old Posted Mar 13, 2012, 2:55 PM
PoscStudent's Avatar
PoscStudent PoscStudent is online now
Registered User
 
Join Date: Jan 2010
Location: St. John's
Posts: 3,752
Quote:
Originally Posted by Marty_Mcfly View Post
There are a few construction pictures floating around the St. John's general thread, I'll check for them after. Progress has been going slowly on the site for months now, though I suspect this is due to the complexity of the grade and requirements for the parking garage.
I was wondering if the sea water heating and cooling system was to blame for the length it's taking to see real progress? I assume that's something they'd need to get done early.
Reply With Quote
     
     
  #7  
Old Posted Mar 13, 2012, 3:00 PM
Marty_Mcfly's Avatar
Marty_Mcfly Marty_Mcfly is offline
Registered User
 
Join Date: Feb 2009
Location: St. John's, NL
Posts: 7,165
Quote:
Originally Posted by PoscStudent View Post
I was wondering if the sea water heating and cooling system was to blame for the length it's taking to see real progress? I assume that's something they'd need to get done early.
I was thinking that as well. Such things require intense drilling on site, which we know is a difficult task here in Newfoundland. However, once all that is done and they start adding floors, I imagine things will go much quicker (like the MUN residence houses).
Reply With Quote
     
     
  #8  
Old Posted Mar 13, 2012, 4:28 PM
PoscStudent's Avatar
PoscStudent PoscStudent is online now
Registered User
 
Join Date: Jan 2010
Location: St. John's
Posts: 3,752
They had those huge pipes too coming from the ground, I don't know what they were for exactly but there's nothing like them at the Fortis site.
Reply With Quote
     
     
  #9  
Old Posted Mar 14, 2012, 12:44 AM
Marty_Mcfly's Avatar
Marty_Mcfly Marty_Mcfly is offline
Registered User
 
Join Date: Feb 2009
Location: St. John's, NL
Posts: 7,165
Quote:
Originally Posted by PoscStudent View Post
They had those huge pipes too coming from the ground, I don't know what they were for exactly but there's nothing like them at the Fortis site.
I'm not sure what those were, but my girlfriend was going on about how those pipes needed anti-corrosion coverings, as her masters in chemistry is about such things. With the Harbour Drive floor being taken care of at this moment, I'd guess that once everything is set and done at that point, the other 11 floors will follow quickly.
Reply With Quote
     
     
  #10  
Old Posted Mar 16, 2012, 1:05 AM
Trend CJ Trend CJ is offline
Registered User
 
Join Date: Dec 2011
Posts: 25
The pics are on Page 171 of the St John's thread. The huge piles they were driving for most of 2010 were for foundation support. That lot is all fill of various ages. I think it took longer than expected to reach solid footing for a building the size of what is going there.
Reply With Quote
     
     
  #11  
Old Posted Mar 20, 2012, 2:26 AM
upnotout upnotout is offline
Registered User
 
Join Date: May 2011
Posts: 50
Just drove by 351 this afternoon. Very busy today. I saw at least ten people as I drove by.
Reply With Quote
     
     
  #12  
Old Posted Mar 21, 2012, 9:00 PM
techie techie is offline
Registered User
 
Join Date: May 2011
Posts: 72
I believe the 300 tonne crane is arriving onsite next week, and the pre cast blocks are going to start arriving in the first week of April. It should start gaining steam quickly now.
Reply With Quote
     
     
  #13  
Old Posted Mar 21, 2012, 9:22 PM
PoscStudent's Avatar
PoscStudent PoscStudent is online now
Registered User
 
Join Date: Jan 2010
Location: St. John's
Posts: 3,752
There's something concrete built up in the centre of the site.
Reply With Quote
     
     
  #14  
Old Posted Mar 22, 2012, 2:18 AM
Marty_Mcfly's Avatar
Marty_Mcfly Marty_Mcfly is offline
Registered User
 
Join Date: Feb 2009
Location: St. John's, NL
Posts: 7,165
Quote:
Originally Posted by PoscStudent View Post
There's something concrete built up in the centre of the site.
Probably the concrete supports that'll be in the building for the parking garage? I hope to get downtown sometime soon (after classes are done) to take pictures of this, Fortis, Star of the Sea and other things.
Reply With Quote
     
     
  #15  
Old Posted Mar 22, 2012, 4:56 AM
Architype's Avatar
Architype Architype is offline
♒︎ Empirically Canadian
 
Join Date: Mar 2004
Location: 🍁 Canada
Posts: 11,902
Quote:
Originally Posted by PoscStudent View Post
There's something concrete built up in the centre of the site.
It may be the service core which will contain the elevator shafts, most likely the stairwells and other vertical servicing shafts.
The plans suggest that the same elevators will be used for both parking and office floors.

Last edited by Architype; Mar 22, 2012 at 5:16 AM.
Reply With Quote
     
     
  #16  
Old Posted Mar 22, 2012, 3:06 PM
AllBlack AllBlack is offline
Registered User
 
Join Date: Oct 2009
Location: St. John's, Newfoundland
Posts: 265
The site is looking much more organized now. Scrap/junk has been hauled away, the 1st floor garage walls are just about complete on the east and west sides, and much of the ground has been compacted inside. Glad to see that things will soon starting looking "up".
Reply With Quote
     
     
  #17  
Old Posted Mar 22, 2012, 4:34 PM
AllBlack AllBlack is offline
Registered User
 
Join Date: Oct 2009
Location: St. John's, Newfoundland
Posts: 265
Signs are posted downtown, closing Harbour Drive March 26 thru March 28.

Assuming this means the arrival of precast panels..?!?
Reply With Quote
     
     
  #18  
Old Posted Mar 22, 2012, 11:53 PM
techie techie is offline
Registered User
 
Join Date: May 2011
Posts: 72
That's just for crane setup. The precast will be arriving over a 6-8 week period.
Reply With Quote
     
     
  #19  
Old Posted Mar 23, 2012, 12:13 AM
statbass statbass is offline
Registered User
 
Join Date: May 2011
Location: St. John's
Posts: 1,650
Quote:
Originally Posted by techie View Post
That's just for crane setup. The precast will be arriving over a 6-8 week period.
Exciting times folks! I can't wait to see the progress over the coming months...
Reply With Quote
     
     
  #20  
Old Posted Mar 23, 2012, 4:53 AM
Architype's Avatar
Architype Architype is offline
♒︎ Empirically Canadian
 
Join Date: Mar 2004
Location: 🍁 Canada
Posts: 11,902
Quote:
Originally Posted by techie View Post
That's just for crane setup. The precast will be arriving over a 6-8 week period.
The crane will be the tallest structure around, for awhile, if it's a real crane.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Atlantic Provinces > St. John's
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 11:17 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.