Quote:
Originally Posted by jsbrook
Whu had said once the building becomes typical - after floor ten - floors will be completed about every 3-4 days. So, that would be even faster. Hope the building as a whole is complete and open by summer of 2018.
|
Based on the drawings that have been released it looks like the western end (15th St) will step inward with in a couple floors, but other then a few minor changes the floor plates look pretty typical already. But I'm not aware of any actual floor plans being released so there's not much to go on.
Has the break down of what hotel chain will occupy which floors been made public? I'm guessing if one chain has the lower floors and the other chain is on the upper floors, that there will be a change, a reduction in the size of the core at the point where the two brands meet.
All this to say once the core gets smaller the pace for completing a floor might pick up alittle. I wonder if the upper floors take any extra time just based on their being that much further off the ground, and more time needed to get manpower and materials to the work area.