AUSTIN | 500 West 2nd Street | 400 FEET | 28 FLOORS | U/C

The address is 500 West 2nd Street.

This is a planned 500,000 square foot office tower that is part of the redevelopment of the old Green Water Treatment Plant. Two other towers in the development will be apartments and the last one will be a hotel.

https://www.austintexas.gov/devrevie...erRSN=11128724
Quote:
The applicant is proposing to construct an office building with associated improvements.
-

Tower crane plans. There will be two cranes. This says the cranes will top out at 547 and 480 feet.
ftp://ftp.ci.austin.tx.us/ATD_AULCC/...rane_PLANS.pdf

-

Here are the heights from the building elevations.

ftp://ftp.ci.austin.tx.us/ATD_AULCC/...20LA_PLANS.pdf
Quote:
399 feet 6 inches to high roof. This is the highest point on the building.

389 feet 6 inches to level 31. This is a mechanical level inside the mechanical penthouse above the main roof.

375 feet 6 inches to level 30. This is another mechanical level.

361 feet 6 inches to "level 29" - this actually the main roof parapet. This would be the barrier wall between you and the "drop."

359 feet 6 inches to "roof" - this is the main roof slab. It's the surface you would walk on on the main roof.

345 feet 6 inches to the 28th floor - this is the highest occupied floor. It's the last office floor.
__________________
Conform or be cast out.
     
     
  #2  
Old Posted Nov 27, 2014, 12:51 AM
KevinFromTexas's Avatar
KevinFromTexas KevinFromTexas is offline
Meh
 
Join Date: Jul 2001
Location: Austin <------------> Birmingham?
Posts: 57,327
Updated renderings.







__________________
Conform or be cast out.
     
     
  #3  
Old Posted Dec 11, 2014, 6:42 AM
KevinFromTexas's Avatar
KevinFromTexas KevinFromTexas is offline
Meh
 
Join Date: Jul 2001
Location: Austin <------------> Birmingham?
Posts: 57,327
Construction to start immediately. Also, they've adopted a new name which will be the building's address - 500 West 2nd Street.

http://www.bizjournals.com/austin/bl....html?page=all
Quote:
Dirt is about to turn for another downtown Austin high-rise
Dec 10, 2014, 10:38am CST

Jan Buchholz
Staff Writer-
Austin Business Journal

Construction will begin immediately on another office tower in downtown Austin. Trammell Crow Co., in association with Principal Real Estate Investors, formally purchased a parcel at the former Green Water Treatment Plant downtown from the city of Austin in the last few days and is proceeding with a speculative office tower.

Beck Commercial Construction is the general contractor on the 29-story, 500,436-square-foot speculative office building at 500 W. Second St. that will be completed by the first quarter of 2017. Gensler is the architect.
Some site work has been done and applications for tower cranes were reported a few weeks ago.
__________________
Conform or be cast out.
     
     
  #4  
Old Posted Jan 23, 2015, 5:52 AM
KevinFromTexas's Avatar
KevinFromTexas KevinFromTexas is offline
Meh
 
Join Date: Jul 2001
Location: Austin <------------> Birmingham?
Posts: 57,327
More renderings















__________________
Conform or be cast out.

Last edited by KevinFromTexas; Jan 25, 2015 at 4:13 AM.
     
     
  #5  
Old Posted Mar 14, 2015, 10:17 PM
KevinFromTexas's Avatar
KevinFromTexas KevinFromTexas is offline
Meh
 
Join Date: Jul 2001
Location: Austin <------------> Birmingham?
Posts: 57,327
http://www.statesman.com/news/busine...owntown/nkWMs/
Quote:
Google to lease 200,000 square feet in new downtown Austin tower

11:50 a.m. Friday, March 13, 2015 | Filed in: Business

Search engine giant Google Inc. is set to establish a major presence in downtown Austin, with plans to lease more than 200,000 square feet of a 29-story office tower being built as part of the redevelopment of the site that once housed the Thomas C. Green Water Treatment Plant.

Gerardo Interiano, public affairs and government relations manager for California-based Google, confirmed the lease in a written statement Friday.
__________________
Conform or be cast out.
     
     
  #6  
Old Posted Apr 20, 2015, 6:37 PM
KevinFromTexas's Avatar
KevinFromTexas KevinFromTexas is offline
Meh
 
Join Date: Jul 2001
Location: Austin <------------> Birmingham?
Posts: 57,327
This is under construction now. They have the rebar for the foundation in place, and they started the mat foundation pour over the weekend. At the moment it would be the 14th tallest in Austin.

https://www.facebook.com/funnyguy82/...7981363660921/
__________________
Conform or be cast out.
     
     
  #7  
Old Posted Apr 21, 2015, 5:53 AM
simms3_redux's Avatar
simms3_redux simms3_redux is offline
She needs her space
 
Join Date: Sep 2005
Location: San Francisco
Posts: 2,454
Austin is on fire!
     
     
  #8  
Old Posted Apr 21, 2015, 7:13 AM
The ATX's Avatar
The ATX The ATX is offline
Moderator
 
Join Date: May 2006
Location: Where the lights are much brighter
Posts: 12,053
This tower is commonly referred to as the Google tower now because Google leased about half of it to consolidate their Austin operations. This is part of the Green Water Development, and there are now rumors in the Austin sub-forum that Facebook is looking to move their Austin operations into another not yet announced Green Water office tower. Facebook's current Austin operations are in another office tower just a few blocks away on W. 6th St.
__________________
Follow The ATX on X:
https://twitter.com/TheATX1

Things will be great when you're downtown.
     
     
  #9  
Old Posted Jun 12, 2015, 1:31 AM
Urbannizer's Avatar
Urbannizer Urbannizer is online now
Moderator
 
Join Date: Jan 2009
Location: 360, St. Edwards
Posts: 12,381
6/10

Camera lens peeking through a hole in the tarp.

     
     
  #10  
Old Posted Jul 13, 2015, 6:35 PM
Urbannizer's Avatar
Urbannizer Urbannizer is online now
Moderator
 
Join Date: Jan 2009
Location: 360, St. Edwards
Posts: 12,381
7/13

__________________
HAIF
     
     
  #11  
Old Posted Aug 4, 2015, 5:27 AM
Urbannizer's Avatar
Urbannizer Urbannizer is online now
Moderator
 
Join Date: Jan 2009
Location: 360, St. Edwards
Posts: 12,381
From today, by me







__________________
HAIF
     
     
  #12  
Old Posted Sep 14, 2015, 4:16 AM
Sic'EmBears's Avatar
Sic'EmBears Sic'EmBears is offline
Registered User
 
Join Date: Sep 2011
Location: Dallas
Posts: 2,221
From my Photobucket this past weekend:

500 W 2nd Street

     
     
  #13  
Old Posted Feb 28, 2016, 4:08 AM
Urbannizer's Avatar
Urbannizer Urbannizer is online now
Moderator
 
Join Date: Jan 2009
Location: 360, St. Edwards
Posts: 12,381
Building Up by M Rasor, on Flickr
__________________
HAIF
     
     
  #14  
Old Posted Jul 9, 2016, 5:07 PM
Urbannizer's Avatar
Urbannizer Urbannizer is online now
Moderator
 
Join Date: Jan 2009
Location: 360, St. Edwards
Posts: 12,381
__________________
HAIF
     
     
  #15  
Old Posted Jul 9, 2016, 8:52 PM
KevinFromTexas's Avatar
KevinFromTexas KevinFromTexas is offline
Meh
 
Join Date: Jul 2001
Location: Austin <------------> Birmingham?
Posts: 57,327
This one is turning out to be one of our biggest buildings.
__________________
Conform or be cast out.
     
     
  #16  
Old Posted Aug 2, 2016, 11:32 PM
KevinFromTexas's Avatar
KevinFromTexas KevinFromTexas is offline
Meh
 
Join Date: Jul 2001
Location: Austin <------------> Birmingham?
Posts: 57,327
8/1





500 West 2nd and University System Headquarters cranes.

__________________
Conform or be cast out.
     
     
  #17  
Old Posted Aug 19, 2016, 12:12 AM
KevinFromTexas's Avatar
KevinFromTexas KevinFromTexas is offline
Meh
 
Join Date: Jul 2001
Location: Austin <------------> Birmingham?
Posts: 57,327
OverAustin pano showing 500 West 2nd Street.

https://www.facebook.com/overaustin/...type=3&theater
__________________
Conform or be cast out.
     
     
  #18  
Old Posted Aug 19, 2016, 9:45 PM
Zerton's Avatar
Zerton Zerton is offline
Ω
 
Join Date: Mar 2002
Location: Chicago
Posts: 4,553
Very nice; modernist. Much better than the Hotel Zaza proposal.
__________________
If all others accepted the lie which the Party imposed, if all records told the same tale, then the lie passed into history and became truth. -Orwell
     
     
  #19  
Old Posted Nov 26, 2016, 5:05 AM
KevinFromTexas's Avatar
KevinFromTexas KevinFromTexas is offline
Meh
 
Join Date: Jul 2001
Location: Austin <------------> Birmingham?
Posts: 57,327
__________________
Conform or be cast out.
     
     
  #20  
Old Posted Nov 29, 2016, 8:09 PM
Urbannizer's Avatar
Urbannizer Urbannizer is online now
Moderator
 
Join Date: Jan 2009
Location: 360, St. Edwards
Posts: 12,381
__________________
HAIF
     
     
End
 
 
 

Go Back   SkyscraperPage Forum > Discussion Forums > Buildings & Architecture > Completed Project Threads Archive
Forum Jump



Forum Jump


All times are GMT. The time now is 1:56 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.