Quote:
Originally Posted by rocketman_95046
How long does that take? Also do you know how many days per floor it is going to take once everything is up and running?
Thanks!
|
Physically jumping the forms only takes a couple hours. The rest of the time in each floor cycle consists of framing, reinforcement, MEP penetrations, and concrete placement.