1198 Commissioners Rd - Tricar Byron condos

Sign has gone up for another Tricar development.

http://www.tricar.com/condos/byron-coming-soon

No artist rendering yet but they have it on their website. The property is across from Springbank park and recently had two homes on it before they were demolished a couple of months ago.

Given size of lot would expect something in the 3-5 story range.
Reply With Quote
     
     
  #2  
Old Posted Dec 16, 2016, 7:51 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,685
Urban Design brief shows this proposed building as a 7 story.
http://www.london.ca/business/Planni...2016-12-21.pdf
Reply With Quote
     
     
  #3  
Old Posted Dec 19, 2016, 3:30 PM
kaiserLDN kaiserLDN is offline
Registered User
 
Join Date: Sep 2016
Location: London
Posts: 385
Nice addition to Byron.
Reply With Quote
     
     
  #4  
Old Posted Dec 22, 2016, 8:41 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,685
Construction is planned to start May 2017 based on todays LFP article.

http://www.lfpress.com/2016/12/22/tr...-road-in-byron

They also had plans for a 22 story on Ridout St near Grand but that has been sitting vacant for a number of years now. Basically the lot has been used as a staging area for the pre-cast concrete slabs going into the Azure condo tower downtown.
Reply With Quote
     
     
  #5  
Old Posted Dec 23, 2016, 2:43 AM
K85's Avatar
K85 K85 is offline
Sanity merchant
 
Join Date: Dec 2010
Posts: 491
*wrong thread*
Reply With Quote
     
     
  #6  
Old Posted Feb 10, 2017, 1:24 PM
MrSlippery519 MrSlippery519 is offline
Registered User
 
Join Date: Dec 2010
Posts: 1,076
Excavator was on site last night (which is new), not sure if they are just continuing to clear the land or are starting early.
Reply With Quote
     
     
  #7  
Old Posted Feb 23, 2017, 12:24 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,685
They were doing a lot of earth movement today with heavy equipment and dump trucks.
Reply With Quote
     
     
  #8  
Old Posted Mar 29, 2017, 3:29 PM
kaiserLDN kaiserLDN is offline
Registered User
 
Join Date: Sep 2016
Location: London
Posts: 385
Excavation is well underway for this project.
Reply With Quote
     
     
  #9  
Old Posted Mar 29, 2017, 3:58 PM
MrSlippery519 MrSlippery519 is offline
Registered User
 
Join Date: Dec 2010
Posts: 1,076
Quote:
Originally Posted by kaiserLDN View Post
Excavation is well underway for this project.
Yep drove by today and the pit for foundation work is further along that I thought it would be.
Reply With Quote
     
     
  #10  
Old Posted Apr 9, 2017, 9:04 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,685
Lots of trees cleared on lot and it appears the home is being prepared for demolition which will free up the entire parcel of land.
Reply With Quote
     
     
  #11  
Old Posted Apr 22, 2017, 11:14 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,685
Home has now been demolished.
Reply With Quote
     
     
  #12  
Old Posted May 29, 2017, 5:08 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,685
Excavation of foundation appears to be nearly complete. Also appears to be deep enough for two levels of underground parking.
Reply With Quote
     
     
  #13  
Old Posted Jun 20, 2017, 10:54 PM
mibb mibb is offline
Registered User
 
Join Date: Jun 2017
Posts: 1
Any new activity??
Reply With Quote
     
     
  #14  
Old Posted Jun 23, 2017, 1:44 PM
MrSlippery519 MrSlippery519 is offline
Registered User
 
Join Date: Dec 2010
Posts: 1,076
They are working daily however not a ton of visible progress has been made.
Reply With Quote
     
     
  #15  
Old Posted Jul 21, 2017, 1:18 PM
MrSlippery519 MrSlippery519 is offline
Registered User
 
Join Date: Dec 2010
Posts: 1,076
Crane is up on the site
Reply With Quote
     
     
  #16  
Old Posted Jul 31, 2017, 10:27 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,685
A lot of steel going into footings for the foundation today.

Expect a lot of concrete will be poured by the end of the week.
Reply With Quote
     
     
  #17  
Old Posted Aug 16, 2017, 10:43 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,685
Steady stream of concrete trucks for foundation pours. Activity level has noticeably increased in last few weeks. Appears there will be 2 levels of underground parking so would expect them to be up to ground level by end of Oct. Standing 7 floors plus mechanical penthouse this building should be topping out by early April 2018.
Reply With Quote
     
     
  #18  
Old Posted Sep 8, 2017, 9:57 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,685
Some of the L2 level concrete walls have been poured as progress continues on the foundation.
Reply With Quote
     
     
  #19  
Old Posted Oct 10, 2017, 10:17 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,685
Setting some of the L1 precast flooring slabs today. Using precast concrete speeds up the process over forming and pouring construction.

If they use precast for the above ground floors they could raise the 7 floors in under 14 weeks.
Reply With Quote
     
     
  #20  
Old Posted Oct 27, 2017, 9:55 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,685
Good progress on the L1 walls and supports. Should be setting the ground level floor within a couple weeks. Would expect the first floor to be mostly done by end of Nov.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 1:26 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.