  #21  
Old Posted Mar 27, 2024, 7:00 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
They have now installed the 4th floor precast concrete floor slabs and have started building the 4th floor concrete block walls for the elevator and stairwell walls.
Reply With Quote
     
     
  #22  
Old Posted Apr 9, 2024, 6:57 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
The 4th floor steel modular wall panels are now being installed on the west wing. Have most of the windows and balcony door modules now installed up to the 3rd floor as well. Would not be surprised to see some of the roof precast concrete slabs being installed next week.
Reply With Quote
     
     
  #23  
Old Posted Apr 24, 2024, 6:51 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
4th floor walls now installed and they have also started installing pre made steel roof panels. First time seeing these per-fabricated roofing panels here in London. They use steel joists and sheets to make a single panel that spans a section. I would expect they would be much lighter weight then concrete precast slabs and engineered for lower loads.
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 2:28 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.