Old Posted Mar 13, 2018, 10:32 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
9th floor walls have started.
Reply With Quote
     
     
  #22  
Old Posted Apr 15, 2018, 12:29 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
10th floor concrete slab pour started this past week. Likely finishing this week and the walls will begin.

Should be topping this out by June.
Reply With Quote
     
     
  #23  
Old Posted Apr 25, 2018, 10:03 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
The 10th fl walls started going up this week.
Reply With Quote
     
     
  #24  
Old Posted May 11, 2018, 10:55 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
Well under way on the 11th floor walls.

12th and final floor will likely be finished by end of May.
Reply With Quote
     
     
  #25  
Old Posted May 15, 2018, 6:57 PM
Djeffery Djeffery is offline
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 4,541
May 15

Reply With Quote
     
     
  #26  
Old Posted May 30, 2018, 10:01 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
Good progress on 12th floor walls. Final floor then mechanical penthouse and this will be topped out.
Reply With Quote
     
     
  #27  
Old Posted Jun 27, 2018, 9:18 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
12 Floor walls are done. Some of the mechanical penthouse is going in and the 12fl roof.

This should be topping out by end of next week.
Reply With Quote
     
     
  #28  
Old Posted Jul 19, 2018, 10:07 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
This is now topped out. They haven't started installing the window and patio door units as of yet.
Reply With Quote
     
     
  #29  
Old Posted Aug 28, 2018, 12:48 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
They finally have started installing windows.
Reply With Quote
     
     
  #30  
Old Posted Sep 7, 2018, 11:00 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
Some windows up to 3rd floor now installed and some work on the balconies. Very slow as it seems like they are tentative with the installations. Wonder if they have run into some fitting problems?
Reply With Quote
     
     
  #31  
Old Posted Sep 15, 2018, 4:05 PM
Neverends Neverends is offline
Registered User
 
Join Date: Sep 2018
Posts: 1
More to come

Some windows up to 3rd floor now installed and some work on the balconies....
Now they are moving the debris, junk and material to the side, to start the new tower; yes another one so the zaga continue for the next few years. The city is all about money, the well been of the residents, the overcrowd of cars with small roads, lack of green zones and planning a friendly neighborhoods have no room in their plans.
Reply With Quote
     
     
  #32  
Old Posted Oct 7, 2018, 12:07 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
Some of the 6th floor windows now installed.
Reply With Quote
     
     
  #33  
Old Posted Oct 19, 2018, 11:10 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
Still only up to the 6th fl with the windows. Really slow progress on the installations.
Reply With Quote
     
     
  #34  
Old Posted Nov 22, 2018, 2:51 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
Still only up to 6th floor with glass. Progress is super slow.
Reply With Quote
     
     
  #35  
Old Posted Dec 11, 2018, 10:55 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
Some windows in now up to 8th floor.
Reply With Quote
     
     
  #36  
Old Posted Jan 11, 2019, 11:56 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
Some of the 12th floor windows finally installed.
Reply With Quote
     
     
  #37  
Old Posted Feb 15, 2019, 11:59 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
Hard to believe they still haven't finished the window and balcony door installations yet.
Reply With Quote
     
     
  #38  
Old Posted Feb 26, 2019, 11:21 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
Well the 12 floor windows and patio doors appear to now be installed. The longest glass installation I've ever seen. If they do the interior drywall at this pace they won't have any tenants until 2020.
Reply With Quote
     
     
  #39  
Old Posted Feb 27, 2019, 2:03 PM
MolsonExport's Avatar
MolsonExport MolsonExport is offline
The Vomit Bag.
 
Join Date: Oct 2003
Location: Otisburgh
Posts: 44,919
DrewloNG
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell)
Reply With Quote
     
     
  #40  
Old Posted May 31, 2019, 8:19 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,792
Tower crane is now gone. Will Drewlo move it behind Lowes or to the Talbot St project next?
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 1:31 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.