Forming now going up for the mechanical penthouse walls on the 23s south tower as the roof slab pour appears to be wrapping up. Sadly there has been no progress installing any of the windows and balcony doors higher then the 6th floor in weeks. They must be having some serious issues with their window and door supplier. Very slow progress with the masonry contractor installing the south side exterior brick on the podium base as well.
|