  #21  
Old Posted Apr 20, 2008, 4:35 AM
caltrane74's Avatar
caltrane74 caltrane74 is offline
gettin' rich!
 
Join Date: Aug 2002
Location: Toronto
Posts: 34,167
Quote:
Originally Posted by Juan_M2118 View Post
But dont they have to reach bedrock,, and where are the caissons?
A1:no clue.

A2:no clue.

crane comes next month.
     
     
  #22  
Old Posted Apr 20, 2008, 1:31 PM
Juan_M2118 Juan_M2118 is offline
Closed account
 
Join Date: Feb 2008
Posts: 49
Quote:
Originally Posted by caltrane74 View Post
A1:no clue.

A2:no clue.

crane comes next month.
Oh wow,, then thats pretty fast. I wish other buildings went up that fast. I cant wait till I see this one up in the sky!
     
     
  #23  
Old Posted Apr 21, 2008, 12:18 AM
caltrane74's Avatar
caltrane74 caltrane74 is offline
gettin' rich!
 
Join Date: Aug 2002
Location: Toronto
Posts: 34,167
Well, it's only because the site is too small for underground parking. If the site had allowed for it, I'm sure they would have dug a little deeper to accomoadate all the luxury cars of the new owners of the real estate in the sky. So it is the site is small and the parking will be above ground and assisted by a car elevator. Like I said, looks like the plan is to have the crane on site by next month. And of course shortly after that we'll see the concrete flowing.
     
     
  #24  
Old Posted Apr 23, 2008, 2:13 AM
caltrane74's Avatar
caltrane74 caltrane74 is offline
gettin' rich!
 
Join Date: Aug 2002
Location: Toronto
Posts: 34,167
They reached bottom.

Juan, where are you bud?




image courtesy of current at www.urbantoronto.ca
     
     
  #25  
Old Posted May 2, 2008, 6:23 PM
caltrane74's Avatar
caltrane74 caltrane74 is offline
gettin' rich!
 
Join Date: Aug 2002
Location: Toronto
Posts: 34,167
still a lot of debris in the pit on this one. Getting a crane in there for May could be a challenge.
     
     
  #26  
Old Posted May 2, 2008, 8:36 PM
M II A II R II K's Avatar
M II A II R II K M II A II R II K is offline
Registered User
 
Join Date: Aug 2002
Location: Toronto
Posts: 52,200
And they for sure would need a much deeper hole for that.
__________________
ASDFGHJK
     
     
  #27  
Old Posted May 3, 2008, 8:04 PM
caltrane74's Avatar
caltrane74 caltrane74 is offline
gettin' rich!
 
Join Date: Aug 2002
Location: Toronto
Posts: 34,167
No that's as deep as they are going to go. 4 floors below ground - 8 above.

But still a lot of debris from the previous building which was on the site, so I don't think the crane will be in there this month as had been promised by the developer. But it's a wait and see thing I guess. We'll find out before the end of the month.
     
     
  #28  
Old Posted May 3, 2008, 9:31 PM
AndrewJ3D AndrewJ3D is offline
Closed account
 
Join Date: Jan 2008
Posts: 348
But don't they need to get down to bedrock still?
     
     
  #29  
Old Posted May 3, 2008, 10:04 PM
WhipperSnapper's Avatar
WhipperSnapper WhipperSnapper is offline
I am the law!
 
Join Date: Sep 2002
Location: Toronto+
Posts: 21,909
^Not with our soil conditions. No caissons, no raft slabs, or both needed in most of Toronto. A 40 foot deep parkade and beefy column footings will more than suffice.

P.S. that hole looks only 3 storeys deep
     
     
  #30  
Old Posted May 9, 2008, 3:26 PM
caltrane74's Avatar
caltrane74 caltrane74 is offline
gettin' rich!
 
Join Date: Aug 2002
Location: Toronto
Posts: 34,167
From NRU, May 9, 2008

Trump tower update
Construction is underway on Toronto’s Trump tower at the corner of Bay and Adelaide streets. Excavation and drilling is nearly complete on the $500-million project that is planned to be a 60-storey hotel and tower with 118-luxury residences and 261-hotel guest rooms and suites. Cranes will be raised on the site during the weekend of May 31 and concrete is scheduled to be poured for the footings of the building shortly thereafter. The building is slated to be complete in 2010. (See NRU Toronto edition September 21, 2007.)
     
     
  #31  
Old Posted May 11, 2008, 8:33 AM
Phil McAvity Phil McAvity is offline
BANNED
 
Join Date: Nov 2006
Location: Victoria
Posts: 3,618
^So now it's 60 stories?

I've heard so many different numbers for floors in this building. The last I heard was 57.
     
     
  #32  
Old Posted May 11, 2008, 6:38 PM
caltrane74's Avatar
caltrane74 caltrane74 is offline
gettin' rich!
 
Join Date: Aug 2002
Location: Toronto
Posts: 34,167
yes, now it's 60 but the height is the same.
     
     
  #33  
Old Posted May 12, 2008, 1:09 PM
caltrane74's Avatar
caltrane74 caltrane74 is offline
gettin' rich!
 
Join Date: Aug 2002
Location: Toronto
Posts: 34,167
New Trump Hoarding



Geekaroo at www.urbantoronto.ca
     
     
  #34  
Old Posted May 27, 2008, 6:46 AM
caltrane74's Avatar
caltrane74 caltrane74 is offline
gettin' rich!
 
Join Date: Aug 2002
Location: Toronto
Posts: 34,167
from drum118 at www.urbantoronto.ca

     
     
  #35  
Old Posted Jun 21, 2008, 11:24 PM
yyzer's Avatar
yyzer yyzer is offline
Registered User
 
Join Date: Apr 2007
Location: Mississauga
Posts: 747
according to a poster over at urbantoronto.ca, the Trump Toronto crane is finally up!
     
     
  #36  
Old Posted Jun 22, 2008, 11:47 PM
caltrane74's Avatar
caltrane74 caltrane74 is offline
gettin' rich!
 
Join Date: Aug 2002
Location: Toronto
Posts: 34,167
Trump crane...

     
     
  #37  
Old Posted Jun 23, 2008, 11:50 PM
yyzer's Avatar
yyzer yyzer is offline
Registered User
 
Join Date: Apr 2007
Location: Mississauga
Posts: 747
2 pics of the Trump Toronto crane, courtesy of Geekaroo over at urbantoronto.ca....



     
     
  #38  
Old Posted Jun 24, 2008, 2:27 PM
10101000 10101000 is offline
Closed account
 
Join Date: May 2007
Posts: 2,832
Nice building, I would love to see that in Mobile.
     
     
  #39  
Old Posted Jun 25, 2008, 11:26 PM
yyzer's Avatar
yyzer yyzer is offline
Registered User
 
Join Date: Apr 2007
Location: Mississauga
Posts: 747
the boom of the Trump Toronto crane swings very close to the surrounding office towers....sure to scare a few people on occasion!

pic by Geekaroo at urbantoronto.ca....

     
     
  #40  
Old Posted Jul 7, 2008, 4:06 PM
caltrane74's Avatar
caltrane74 caltrane74 is offline
gettin' rich!
 
Join Date: Aug 2002
Location: Toronto
Posts: 34,167
Good to see this project really moving now.
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
 

Go Back   SkyscraperPage Forum > Discussion Forums > Buildings & Architecture > Completed Project Threads Archive
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 10:03 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.