Winnipeg | Red River College | Innovation Centre Exchange District campus | U/C

Location: Winnipeg, MB, Downtown Exchange District Campus
Architect: Number TEN Architectural Group and Diamond Schmitt Architects inc. https://www.numberten.com/projects/i...-river-college
Client: Red River College http://blogs.rrc.ca/edc/
Size: 100,000 sq. ft.
Completed: 2020 (targeted)
Budget: $95 M
Video:
Video Link


Quote:
INNOVATION CENTRE @ RED RIVER COLLEGE
Red River College is in a period of growth, with current demand for innovative programming pushing the limits of its physical infrastructure. To compliment and enhance existing programs, improve its overall competitiveness, and better meet the needs of small to medium enterprises in Winnipeg’s downtown, the college secured funding for a new Innovation Centre at its Exchange District Campus.

Number TEN Architectural Group in joint venture with Diamond Schmitt Architects Inc. has been working with a diverse group of Red River College stakeholders to develop the design for the new facility. Living up to its name, the new Innovation Centre @ RRC will be one of the most advanced and forward-thinking buildings of its kind in Canada. Targeting net zero energy, the Innovation Centre will emit little to no net carbon emissions – an ambitious goal considering Winnipeg’s extreme prairie climate.

Inspired by its site context, the 100,000 sq. ft. Innovation Centre is designed to look to the future while respecting the past. The project includes the adaptive re-use of the historically designated Scott Fruit building adjacent to Red River College’s existing Roblin Centre, a state-of-the-art four-storey addition, and an above-ground pedestrian walkway connecting to the Roblin Centre. The skin of the new building addition is comprised of photovoltaic glass that generates energy and changes colour according to weather and the angle in which it is viewed.

Inside, a wide array of unique light-filled programming, circulation and multi-purpose collaboration space is designed to inspire students, create a sense of wonder and encourage idea sharing between students, staff, and industry partners. Indigenous design elements and artwork will form a deeper connection with the site, its history and the surrounding community.

Currently in the construction phase, the Innovation Centre @RRC is on track to welcome up to 1,200 new students in the fall of 2020 and is anticipated to provide an economic boost to downtown Winnipeg and the surrounding Exchange District.
Location:





















Quote:
RED RIVER COLLEGE’S NEW 100,000 SQ. FT. INNOVATION CENTRE BREAKS GROUND
Published: Wednesday, 18 July 2018 10:30
Shovels hit the ground Wednesday July 18 at Red River College’s Exchange District Campus, on the site of what will become the new Innovation Centre @ RRC. In front of a distinguished audience of dignitaries and project stakeholders, RRC executive director of Indigenous strategy Rebecca Chartrand blessed the site on behalf of campus elders.

The new Innovation Centre is designed to foster collaboration between students, faculty, industry and the community, leading to new ideas and partnerships that support the college’s goal of preparing students for the job market and moving local industry ahead of the curve. Designed by Number TEN Architectural Group and Diamond Schmitt Architects inc. in joint venture, the facility’s striking design features will capture the imagination of both building users and passersby.

“During the design process, we proposed that wonder, Imagination, empathy, mystery, being startled, and engaging in passionate search are the key experiences underpinning innovation,” said Number TEN partner-in-charge Doug Hanna in his address to the audience. “In our search for additional layers of meaning that complemented the project charter, it was our intention that the Innovation Centre @ Red River College inspire these qualities in students and faculty.”

The Innovation Centre’s project charter – a set of established and agreed upon project objectives – includes the following goals:
• Community connectivity, inclusion and collaboration
• Socially responsible programs and initiatives
• Agility and adaptability to enhance innovation
• Unique architectural design relevant to innovative learning and teaching
• Heritage adaptive re-use sensitive to the exchange district
• Leading edge sustainability

Among the project’s most ambitious goals is its net zero emissions energy target – a first for a project of this scale in Manitoba. A net zero building is one where the total energy consumed annually is approximately equal to the amount of renewable energy created on the site and returned to the grid.

Last edited by Wpg_Guy; Oct 2, 2018 at 9:56 PM.
Reply With Quote
     
     
  #2  
Old Posted Jul 18, 2018, 10:09 PM
Wpg_Guy's Avatar
Wpg_Guy Wpg_Guy is offline
Registered User
 
Join Date: Aug 2002
Location: Winnipeg, Manitoba, Canada
Posts: 2,708






Reply With Quote
     
     
  #3  
Old Posted Jul 19, 2018, 1:50 AM
Design-mind's Avatar
Design-mind Design-mind is offline
Registered User
 
Join Date: Oct 2012
Posts: 4,591
Love the design! With the Innovation Centre & Market lands coming on board this area will become so walkable and trendy.
Reply With Quote
     
     
  #4  
Old Posted Jul 19, 2018, 2:08 AM
GlassCity's Avatar
GlassCity GlassCity is offline
Registered User
 
Join Date: Aug 2012
Location: Vancouver/[Winnipeg]
Posts: 4,923
Looks great, thanks for posting! Look forward to following along.
Reply With Quote
     
     
  #5  
Old Posted Sep 2, 2018, 7:59 PM
Wpg_Guy's Avatar
Wpg_Guy Wpg_Guy is offline
Registered User
 
Join Date: Aug 2002
Location: Winnipeg, Manitoba, Canada
Posts: 2,708

https://instagram.fybz2-1.fna.fbcdn....63348398_n.jpg
Tomasz Fiertek (@tomaszfiertek) on Instagram
Reply With Quote
     
     
  #6  
Old Posted Sep 26, 2018, 12:23 AM
Wpg_Guy's Avatar
Wpg_Guy Wpg_Guy is offline
Registered User
 
Join Date: Aug 2002
Location: Winnipeg, Manitoba, Canada
Posts: 2,708

https://media.winnipegfreepress.com/...NEP4810631.jpg


https://media.winnipegfreepress.com/...NEP4810630.jpg


https://media.winnipegfreepress.com/...NEP4810629.jpg

Quote:
RRC builds on innovative approach to education
Construction underway on college's new facility
Martin Cash By: Martin Cash
Posted: 09/26/2018 6:30 PM

The excavation and piling work has begun on Red River College’s $95-million Innovation Centre just north of the Roblin Building on its Princess campus, and is on schedule to be completed in the fall of 2020.

The building is necessary for purely expansionary reasons and will bring an additional 1,200 students and staff to the Exchange District on top of the 2,500 already there.

And, in addition to the innovative approach to the manner in which RRC will provide education, the building itself includes lots of innovative features.

For starters, the 100,000-square-foot building on Elgin Street will fully integrate a 100-year-old, three-storey building that happens to be one of the first buildings in the city to use concrete construction instead of timber.

"The vertical concrete columns are as thick as the timbers that were being used in construction," said Maria Mendes, RRC’s senior project manager. "It is a sound building. It has not moved in 100 years."

The building is being designed specifically to encourage collaboration and multi-disciplinary team work, so there won’t be classrooms with desks all facing the front. The walls that will be there will mostly be made of glass.

"It is an approach to collaborative learning that’s very different from the way we have done education in the past," RRC president Paul Vogt said. "What employers increasingly tell us is they are looking for that cluster of what we used to call soft skills, but are now being described as power skills or 21st-century skills."

Conceptually, that sounds reasonable. But, practically pulling that off in a $95-million building seems risky.

But,the open-design concept is not being dreamed up by RRC folks in a vacuum. In addition to design assistance being provided by Number Ten Architectural Group, the main architects are Diamond Schmitt Architects with offices in Toronto, Vancouver and New York, who have been responsible for the recent design work at a number of other collaborative learning facilities at institutions, including Emily Carr University of Art and Design in Vancouver, Lazaridis Hall at Wilfrid Laurier University in Waterloo, Ont., the Papadakis Integrated Sciences Building at Drexel University in Philadelphia and the Schulich School of Engineering at the University of Calgary.

"Buildings designed for collaborative education are being developed across North America and Europe," Vogt said. "These kinds of spaces have been tested out already. They are highly functional for the kind of education we are doing and for bringing business and the community into an educational setting."

The plan is for the building to be open in the evenings and on weekends to accommodate re-skilling courses that are expected to be a growth area for RRC.

Part of the old building — the Scott Fruit Company Warehouse — will be used to house RRC’s successful Ace Project Space, now being offered in conjunction with North Forge Technology Exchange. It allows students to work with existing entrepreneurs or startups on company projects.

Vogt sometimes refers to the Innovation Centre as Ace Space super-sized.

"It is not entirely a leap into the dark." he said. "With Ace Space, it is a tested model and it works.

"We are very confident in expanding it."

The Innovation Centre will be flexible enough to include broad multi-disciplinary programs to allow for expanded business and business IT, and design and computer-design programs.

Designed as a net-zero building — it will generate as much energy as it uses — it will include photovoltaic cells on the roof of the Scott building and innovative vertical PV cells on the south wall of the new building. It will also experiment with Power-Over-Ethernet technology for some of the lighting in the building, and all sorts of specialized design has been integrated for optimal acoustic effect throughout the building.

Mendes said using big data, RRC’s design consultants came up with 260,000 different models to achieve the kind of energy and performance efficiencies it was looking for.

"Then we narrowed it down to four, and it was like a shopping list," she said. "We were able to play with all the different elements and tweak it so we can be as cost effective and efficient as possible."

The second floor will feature a 210-seat flexible auditorium designed as a building within a building. It will be the downtown campus’s first auditorium of that size.

martin.cash@freepress.mb.ca
https://www.winnipegfreepress.com/bu...494314401.html
Reply With Quote
     
     
  #7  
Old Posted Oct 2, 2018, 9:55 PM
Wpg_Guy's Avatar
Wpg_Guy Wpg_Guy is offline
Registered User
 
Join Date: Aug 2002
Location: Winnipeg, Manitoba, Canada
Posts: 2,708
Quote:
Ramping up momentum for College’s new Innovation Centre
September 27, 2018

You’re about to start hearing a lot more about Red River College’s new Innovation Centre, construction of which is already underway in Winnipeg’s Exchange District.

The conversation started this week with a keynote speech from RRC President Paul Vogt to the members of the Manitoba Chambers of Commerce, and with a feature article in the Winnipeg Free Press by Business writer Martin Cash.

Slated for completion in the fall of 2020, the $95-million, 100,000-sq. ft. facility will be a hub for innovation and collaboration — one that will continue to grow Winnipeg’s technology and business sectors, with a focus on applied research, entrepreneurship and social innovation.

It will feature adaptable classrooms, collaboration spaces, an array of student services and supports, and — at its heart — a roundhouse auditorium with seating for 210 people.

With more than 21,000 students enrolled annually, the College is currently operating at capacity, and needs to expand to continue meeting the ever-changing industry requirements of the businesses and organizations where graduates find employment.

This new facility will help RRC students remain ahead of the curve, armed with the knowledge and skills required to start their new careers as leaders.

Learn more about how you can get involved with the Innovation Centre project.
https://www.rrc.ca/news/2018/09/27/r...vation-centre/
Video Link
Reply With Quote
     
     
  #8  
Old Posted Oct 5, 2018, 5:06 PM
Wpg_Guy's Avatar
Wpg_Guy Wpg_Guy is offline
Registered User
 
Join Date: Aug 2002
Location: Winnipeg, Manitoba, Canada
Posts: 2,708
Akman Construction Ltd. on Instagram: “Piling is underway at Red River College’s - Innovation Centre!






https://www.instagram.com/p/BojVxpPn...n_construction
Reply With Quote
     
     
  #9  
Old Posted Yesterday, 4:09 AM
Wpg_Guy's Avatar
Wpg_Guy Wpg_Guy is offline
Registered User
 
Join Date: Aug 2002
Location: Winnipeg, Manitoba, Canada
Posts: 2,708
Update
Quote:
Originally Posted by Kildonaner View Post
Just setup a new construction camera system on the NW corner of the Adelaide building to monitor construction progress over the next 3 years! It's a solar powered and weatherproof Canon DSLR system that requires me to manually retrieve the photos every couple weeks. Here is a shot from above, piles currently going in.


Quote:
Originally Posted by Kildonaner View Post
Piles are in (as of Oct 26th) and the last pic before the snow covered the site


Nov 6th, 2018
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Global Projects & Construction > General Development
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 1:32 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2018, vBulletin Solutions, Inc.